Summary for Test 2023-09-29-40-1

Test performed: CTM 552-December 2013

Project Information

Project IdentifiersProject ID: 993807
DEA: 07353304
EFIS: 0718000272
DIST-CO-RTE-PM07-LA-110-23.1
Award Date11/03/2022
Closeout Date09/24/2024
Work DescriptionREPLACE BRIDGE RAILING WITH CONCRETE BARRIER. AND UPGRADE LIGHTING.
Location DescriptionLOS ANGELES COUNTY IN LOS ANGELES AT THIRD STREET OVERCROSSING
QA Service Level1 (Verified on 05/11/2022)

Sample Information

Sample Taken Date09/29/2023 Sample Unique Key40
Date that the sample was received by the laboratory/organization performing the testing09/29/2023 Sample typeDepartment Acceptance
A brief description of the sampleRelative Compaction of Polymer Concrete The quantity of what the sample constitutesUnverifiable
From where was the sample collectedJob Site First name of sampler or witnessed byPhilip
Last name of sampler or witnessed byMaquiran Title of samplerMREA
Telephone number of sampler(213) 358-1518 Laboratory sample identification23-1508
Linked DIME Sample ID The fabricator/manufacturer/facility namePowell Construcion
Transportation Laboratory (TL) Number Inspector Lot Number from the Transportation Laboratory (TL) Form
Structure unique identifier Structure name
Bid ItemNot set

Material Information

Material TypePolyester Mfg. Lot Number(s)Unverifiable
Batch Number1 Mix numberUnverifiable

Test Details

DIME Sample ID: 2023-09-29-40
DIME Test ID: 2023-09-29-40-1
Testing Lab: CT D07 - Materials Field Laboratory, Unit 1953
Test Method: CTM 552-December 2013: Method of Test for Relative Compaction of Polymer Concrete Utilizing Nuclear Gages
Test Release Date: 2023-10-11

Test Results


Input Type: Calculated
Tester's full name: Phillip Maquiran
Date of test: 09/29/2023
Gage No.: 63090
Time of test: 01:05 HH:MM
Standard Density: 2.23 g/cc
In-Place Density: 2.18 g/cc
Percent Relative Compaction: 98 %
General comments (publicly viewable) (Max 1000 characters):

Test was verified on 10/11/2023 ✔