Project Information
Project Identifiers | Project ID: 212112 DEA: 080C2514 EFIS: 0816000076 COOP: 081645 |
---|---|
DIST-CO-RTE-PM | 08-SBD-10-0.0/13.2 |
Award Date | 06/06/2018 |
Closeout Date | Not set |
Work Description | Design-Build of I-10 Corridor Contract 1 - Adding 2 new Express Lanes |
Location Description | LA/SBD County Line to PM 13.2 near I-15 |
QA Service Level | 1 (Verified on 10/16/2019) |
Sample Information
Sample Taken Date | 10/26/2023 | Sample Unique Key | 46 |
---|---|---|---|
Will the laboratory/organization for which you are a member perform testing on this material sample? | Yes | Date that the sample was received by the laboratory/organization performing the testing | 11/02/2023 |
Sample type | Department Acceptance | A brief description of the sample | 3/4" HMA-A SP R15 0.5% LAS |
The quantity of what the sample constitutes | 2 BOXES OF HMA | From where was the sample collected | Manufacturer |
First name of sampler or witnessed by | VULCAN | Last name of sampler or witnessed by | QC |
Title of sampler | Telephone number of sampler | ||
Laboratory sample identification | QC | Linked DIME Sample ID | |
The fabricator/manufacturer/facility name | VULCAN | Transportation Laboratory (TL) Number | |
Inspector Lot Number from the Transportation Laboratory (TL) Form | Structure unique identifier | ||
Structure name |
Material Information
Material Type | Hot Mix Asphalt | HMA Type | Type A HMA |
---|---|---|---|
HMA Grading | 3/4 inch | Lot number | |
Sublot number | HMA Mix Number | 224112A IRW SJR |
Submitted Tests
Sample File Attachments
File Name | Extension | Date Uploaded | Actions |
---|---|---|---|
No results found. |
Test File Attachments
DIME Test ID: 2023-10-26-46-1 AASHTO T308-10 (Verified)