Sample Record
Owner Lab
- CT HQ - FFS - Skid Testing
DIME Sample ID 2023-06-25-1
Project Information
Project Identifiers | Project ID: 214988 DEA: 050L7214 EFIS: 0515000097 |
---|---|
DIST-CO-RTE-PM | 05-SLO-1-32.6 |
Award Date | 03/08/2021 |
Closeout Date | Not set |
Work Description | REMOVE & CONSTRUCT CONCRETE BRIDGE, CONCRETE SLAB, BRIDGE RAIL & HMA. |
Location Description | SAN LUIS OBISPO COUNTY IN MORRO BAY AT TORO CREEK BRIDGE |
QA Service Level | 1 (Verified on 09/03/2020) |
Sample Information
Sample Taken Date | 06/25/2023 | Sample Unique Key | 1 |
---|---|---|---|
Will the laboratory/organization for which you are a member perform testing on this material sample? | Yes | Date that the sample was received by the laboratory/organization performing the testing | 06/25/2023 |
Sample type | Acceptance | A brief description of the sample | PCC |
The quantity of what the sample constitutes | BRIDGE | From where was the sample collected | Job Site |
First name of sampler or witnessed by | HARISH | Last name of sampler or witnessed by | Thakur |
Title of sampler | Telephone number of sampler | 9152961873 | |
Laboratory sample identification | Linked DIME Sample ID | ||
The fabricator/manufacturer/facility name | BRIDGE | Transportation Laboratory (TL) Number | |
Inspector Lot Number from the Transportation Laboratory (TL) Form | Structure unique identifier | ||
Structure name |
Material Information
Material Type | Roadway/Bridge Surface | Pavement Surface Type | Not set |
---|---|---|---|
Type of Traffic Control Provided | Not set | DIST-CO-RTE | Not set |
Direction of Travel | Not set | Post Mile | Not set |
Lanes to be Tested | Not set | Station | Not set |
Submitted Tests
Sample File Attachments
File Name | Extension | Date Uploaded | Actions |
---|---|---|---|
No results found. |
Test File Attachments
DIME Test ID: 2023-06-25-1-1 CTM 342-August 2012 (Verified)
DIME Test ID: 2023-06-25-1-2 CTM 342-August 2012 (Verified)
DIME Test ID: 2023-06-25-1-3 CTM 342-August 2012 (Verified)