Sample Record

Owner Lab

  • CT D09 - Bishop Field Laboratory

DIME Sample ID 2023-08-23-61

Sample is locked from editing. info

Project Information

Project IdentifiersProject ID: 993685
DEA: 09382304
EFIS: 0919000038
DIST-CO-RTE-PM09-KER,MNO-395-Var
Award DateNot set
Closeout DateNot set
Work DescriptionFURNISH AND INSTALL SIGN STRUCTURE (TRUSS); AND PLACE AND MODIFY CMS.
Location DescriptionKERN AND MONO COUNTIES AT VARIOUS LOCATIONS
QA Service Level1 (Verified on 10/31/2022)

Sample Information

Sample Taken Date08/23/2023 Sample Unique Key61
Will the laboratory/organization for which you are a member perform testing on this material sample?Yes Date that the sample was received by the laboratory/organization performing the testing08/28/2023
Sample typeAcceptance A brief description of the sampleStructural PCC
The quantity of what the sample constitutes12 PCC 4x8 Cylinders From where was the sample collectedJob Site
First name of sampler or witnessed byDerek Last name of sampler or witnessed byArmon
Title of samplerStructures Rep Telephone number of sampler
Laboratory sample identificationPCC-01 Linked DIME Sample ID
The fabricator/manufacturer/facility nameMammoth ready mix Transportation Laboratory (TL) Number
Inspector Lot Number from the Transportation Laboratory (TL) Form Structure unique identifier
Structure nameCMS LOC 2

Material Information

Material TypeConcrete The concrete mix design number1304-18-25A
The truck number from where the sample was collected The batch plant ticket number from where the sample was collectedTruck 1
Concrete batch plant The fabricator/manufacturer designation for the sample
A detailed description of where the material sample was collectedMiddle of Truck 1 Where the material sample would have been placed if not sampled
From Lot No. Bag Lot No.

Submitted Tests

DIME Test IDTest MethodTester Name, Testing LabDate TestedSubmitted ByVerified?Release DateTest CommentsActions
2023-08-23-61-1CTM 521-June 2020: Method of Test for Compressive Strength of Molded Concrete CylindersDerek Carrington, CT D09 - Bishop Field Laboratory08/30/2023Derek Carrington
Yes
08/30/20237 Day Break
2023-08-23-61-2CTM 521-June 2020: Method of Test for Compressive Strength of Molded Concrete CylindersDerek Carrington, CT D09 - Bishop Field Laboratory09/20/2023Derek Carrington
Yes
09/20/202328 Day Break

Sample File Attachments

File NameExtensionDate UploadedActions
No results found.

Test File Attachments


DIME Test ID: 2023-08-23-61-1 CTM 521-June 2020 (Verified)
DIME Test ID: 2023-08-23-61-2 CTM 521-June 2020 (Verified)