Sample Record

Owner Lab

  • CT HQ - Sacramento Structural Materials Testing Laboratory

DIME Sample ID 2021-05-28-16

Sample is locked from editing. info

Project Information

Project IdentifiersProject ID: 215129
DEA: 050N73U4
EFIS: 0520000166
DIST-CO-RTE-PM05-SB-101-7.3/9.6
Award Date10/23/2020
Closeout DateNot set
Work Description!!Please CC Office Engineer Gabrielle Herrera on reports to RE and SR!! Segment 4C - Summerland: Construct HOV lanes and rehabilitation. Source inspection of sign structure trusses, lighting structures, steel soldier piles, epoxy coated rebar,
Location DescriptionSUMMERLAND FROM 0.2 MILES NORTH OF PARDARO LANE OVERCROSSING TO SAN YSIDRO CREEK BRIDGE
QA Service Level1 (Verified on 08/24/2020)

Sample Information

Sample Taken Date05/28/2021 Sample Unique Key16
Will the laboratory/organization for which you are a member perform testing on this material sample?Yes Date that the sample was received by the laboratory/organization performing the testing06/03/2021
Sample typeQuality Assurance A brief description of the sampleErico Lenton Stander A2 Couplers
The quantity of what the sample constitutes4 From where was the sample collectedJob Site
First name of sampler or witnessed byEmiliano Last name of sampler or witnessed byBerntsen
Title of sampler Telephone number of sampler
Laboratory sample identification Linked DIME Sample ID
The fabricator/manufacturer/facility nameCMC Erico Transportation Laboratory (TL) NumberC760216
Inspector Lot Number from the Transportation Laboratory (TL) Form Structure unique identifier
Structure name

Material Information

Material TypeSMTL TM5 - Couplers Production or Authorization TestingProduction Testing
Service or UltimateService Material Standard CodeASTM A706
Material Grade60 Rebar ManufacturerCMC Rebar
Coupler ManufacturerErico Lenton Intermediate Assembler or Fabricator
Rebar Size#6 Coupler ModelErico Lenton Stander A2 Couplers
Coating StandardsASTM A934 epoxy Shape of RebarStraight
Rebar Hoop Diameter Rebar Hoop Fabricator
Coupler Component Heat/Lot Number(s)L9476 Rebar Heat Number(s)4103432
Rebar Size 2 Coupler Unique IDNot set

Submitted Tests

DIME Test IDTest MethodTester Name, Testing LabDate TestedSubmitted ByVerified?Release DateTest CommentsActions
2021-05-28-16-1CTM 670-December 2013: Method of Tests for Mechanical and Welded Reinforcing Steel Splices (Cyclical/Fatique Tensile with Slip)fsaylor, CT HQ - Sacramento Structural Materials Testing Laboratory06/03/2021fsaylor
Yes
06/04/2021Service Splice
2021-05-28-16-2CTM 670-December 2013: Method of Tests for Mechanical and Welded Reinforcing Steel Splices (Cyclical/Fatique Tensile with Slip)fsaylor, CT HQ - Sacramento Structural Materials Testing Laboratory06/03/2021fsaylor
Yes
06/04/2021Service Splice
2021-05-28-16-3CTM 670-December 2013: Method of Tests for Mechanical and Welded Reinforcing Steel Splices (Cyclical/Fatique Tensile with Slip)fsaylor, CT HQ - Sacramento Structural Materials Testing Laboratory06/03/2021fsaylor
Yes
06/04/2021Service Splice

Sample File Attachments

File NameExtensionDate UploadedActions
No results found.

Test File Attachments


DIME Test ID: 2021-05-28-16-1 CTM 670-December 2013 (Verified)
DIME Test ID: 2021-05-28-16-2 CTM 670-December 2013 (Verified)
DIME Test ID: 2021-05-28-16-3 CTM 670-December 2013 (Verified)