Sample Record
Owner Lab
- CT HQ - Sacramento Structural Materials Testing Laboratory
DIME Sample ID 2020-12-07-2
Project Information
Project Identifiers | Project ID: 99999 DEA: 0322222 |
---|---|
DIST-CO-RTE-PM | 03-SAC,OMG-888,99,80-0.6-0.6 |
Award Date | Not set |
Closeout Date | Not set |
Work Description | THIS PROJECT RECORD WAS ADDED FOR DIME TESTERS - DATA SUBMITTED FOR THIS PROJECT SHOULD NOT BE USED FOR ANY OTHER PURPOSES. |
Location Description | THIS PROJECT RECORD WAS ADDED FOR DIME TESTERS - DATA SUBMITTED FOR THIS PROJECT SHOULD NOT BE USED FOR ANY OTHER PURPOSES. |
QA Service Level | (Verified on 04/05/2013) |
Sample Information
Sample Taken Date | 12/07/2020 | Sample Unique Key | 2 |
---|---|---|---|
Will the laboratory/organization for which you are a member perform testing on this material sample? | Yes | Date that the sample was received by the laboratory/organization performing the testing | 12/07/2020 |
Sample type | Authorization | A brief description of the sample | #4 service splice coupler |
The quantity of what the sample constitutes | 4 | From where was the sample collected | Fabricator |
First name of sampler or witnessed by | David | Last name of sampler or witnessed by | Murray |
Title of sampler | Materials Engineer | Telephone number of sampler | 9136395549 |
Laboratory sample identification | NA | Linked DIME Sample ID | |
The fabricator/manufacturer/facility name | Erico | Transportation Laboratory (TL) Number | |
Inspector Lot Number from the Transportation Laboratory (TL) Form | Structure unique identifier | ||
Structure name |
Material Information
Material Type | SMTL TM5 - Couplers | Production or Authorization Testing | Authorization Testing |
---|---|---|---|
Service or Ultimate | Service | Material Standard Code | ASTM A706 |
Material Grade | 60 | Rebar Manufacturer | Cascade |
Coupler Manufacturer | Erico | Intermediate Assembler or Fabricator | |
Rebar Size | #4 | Coupler Model | Mechanical |
Coating Standards | Uncoated | Shape of Rebar | Straight |
Rebar Hoop Diameter | Rebar Hoop Fabricator | ||
Coupler Component Heat/Lot Number(s) | MM18108717/0007 | Rebar Heat Number(s) | 261520 |
Rebar Size 2 | Coupler Unique ID | Not set |
Submitted Tests
DIME Test ID | Test Method | Tester Name, Testing Lab | Date Tested | Submitted By | Verified? | Release Date | Test Comments | Actions |
---|---|---|---|---|---|---|---|---|
2020-12-07-2-1 | CTM 670-December 2013: Method of Tests for Mechanical and Welded Reinforcing Steel Splices (Cyclical/Fatique Tensile with Slip) | fsaylor, CT HQ - Sacramento Structural Materials Testing Laboratory | 01/15/2021 | fsaylor | No | 10K Service Splice | Info | |
2020-12-07-2-2 | CTM 670-December 2013: Method of Tests for Mechanical and Welded Reinforcing Steel Splices (Cyclical/Fatique Tensile with Slip) | fsaylor, CT HQ - Sacramento Structural Materials Testing Laboratory | 01/15/2021 | fsaylor | No | 100 cycle Service Splice | Info | |
2020-12-07-2-3 | CTM 670-December 2013: Method of Tests for Mechanical and Welded Reinforcing Steel Splices (Cyclical/Fatique Tensile with Slip) | fsaylor, CT HQ - Sacramento Structural Materials Testing Laboratory | 01/15/2021 | fsaylor | No | Service Splice | Info | |
2020-12-07-2-4 | CTM 670-December 2013: Method of Tests for Mechanical and Welded Reinforcing Steel Splices (Cyclical/Fatique Tensile with Slip) | fsaylor, CT HQ - Sacramento Structural Materials Testing Laboratory | 01/15/2021 | fsaylor | No | Service Splice | Info |
Sample File Attachments
File Name | Extension | Date Uploaded | Actions |
---|---|---|---|
No results found. |
Test File Attachments
DIME Test ID: 2020-12-07-2-1 CTM 670-December 2013
DIME Test ID: 2020-12-07-2-2 CTM 670-December 2013
DIME Test ID: 2020-12-07-2-3 CTM 670-December 2013
DIME Test ID: 2020-12-07-2-4 CTM 670-December 2013