Sample Record
DIME Sample ID 2022-10-24-39
Project Information
| Project Identifiers | Project ID: 994270 DEA: 072XC004 EFIS: 0723000026 |
|---|---|
| DIST-CO-RTE-PM | 07-LA,LA/LA-5-62.12/62.3, 61.5/64.3, R61.5R +R61.2L/R63.7R +R64.3L, R61.5R/R63.7R |
| Award Date | 09/01/2022 |
| Closeout Date | 11/07/2024 |
| Work Description | LA-5 Remove and replace fire timber lagging retaining wall |
| Location Description | I5N Near Castaic PM 62.12 and 62.3 |
| QA Service Level | 1 (Verified on 09/19/2022) |
Owner Lab
- CT D07 - Materials Field Laboratory, Unit 1953
Sample Information
| Sample Taken Date | 10/24/2022 | Sample Unique Key | 39 |
|---|---|---|---|
| Date that the sample was received by the laboratory/organization performing the testing | 10/28/2022 | Sample type | Department Acceptance |
| A brief description of the sample | 6X12 PCC cylinder | The quantity of what the sample constitutes | 130 CY |
| From where was the sample collected | Job Site | First name of sampler or witnessed by | Torch |
| Last name of sampler or witnessed by | Rivera | Title of sampler | Assistant Structure Representative |
| Telephone number of sampler | Laboratory sample identification | 22-0333 | |
| Linked DIME Sample ID | The fabricator/manufacturer/facility name | Security Paving | |
| Transportation Laboratory (TL) Number | 25 | Inspector Lot Number from the Transportation Laboratory (TL) Form | |
| Structure unique identifier | Structure name | ||
| Bid Item | Not set |
Material Information
| Material Type | Concrete | The concrete mix design number | S85C440T14 |
|---|---|---|---|
| The truck number from where the sample was collected | NA | The batch plant ticket number from where the sample was collected | NA |
| Concrete batch plant | Security Paving | The fabricator/manufacturer designation for the sample | |
| A detailed description of where the material sample was collected | truck chute | Where the material sample would have been placed if not sampled | |
| From Lot No. | Bag Lot No. |
Submitted Tests
Sample File Attachments
| File Name | Extension | Date Uploaded | Actions |
|---|---|---|---|
| No results found. | |||
Test File Attachments
DIME Test ID: 2022-10-24-39-1 CTM 521-June 2020 (Verified)
DIME Test ID: 2022-10-24-39-2 CTM 521-June 2020 (Verified)