Sample Record

Owner Lab

  • CT D08 - Fontana Southern Regional Laboratory

DIME Sample ID 2022-12-07-17

Project Information

Project IdentifiersProject ID: 212112
DEA: 080C2514
EFIS: 0816000076
COOP: 081645
DIST-CO-RTE-PM08-SBD-10-0.0/13.2
Award Date06/06/2018
Closeout DateNot set
Work DescriptionDesign-Build of I-10 Corridor Contract 1 - Adding 2 new Express Lanes
Location DescriptionLA/SBD County Line to PM 13.2 near I-15
QA Service Level1 (Verified on 10/16/2019)

Sample Information

Sample Taken Date12/07/2022 Sample Unique Key17
Date that the sample was received by the laboratory/organization performing the testing12/09/2022 Sample typeQuality Assurance
A brief description of the sampleConcrete Cylinders The quantity of what the sample constitutes4
From where was the sample collectedJob Site First name of sampler or witnessed byEdwardo
Last name of sampler or witnessed byGomez Title of samplerQA Inspector
Telephone number of sampler Laboratory sample identification1015-1207
Linked DIME Sample ID2022-12-07-17 The fabricator/manufacturer/facility nameLane Security Joint Venture
Transportation Laboratory (TL) Number1 Inspector Lot Number from the Transportation Laboratory (TL) Form
Structure unique identifier Structure name
Bid ItemNot set

Material Information

Material TypeConcrete The concrete mix design number1613385
The truck number from where the sample was collected10064186 The batch plant ticket number from where the sample was collected52261072
Concrete batch plantCemex Corona The fabricator/manufacturer designation for the sample
A detailed description of where the material sample was collectedElc Frame 3 - 2 Span 10 and 11 Deck Pour Load 17 Where the material sample would have been placed if not sampled
From Lot No. Bag Lot No.

Submitted Tests

DIME Test IDTest MethodTester Name, Testing LabDate TestedDate AddedVerified?Release DateTest CommentsPrivacy LevelActions
No results found.

Sample File Attachments

File NameExtensionDate UploadedActions
No results found.

Test File Attachments