Summary for Test 2019-01-17-11-1
Test performed: AASHTO T30-15Project Information
Project Identifiers | Project ID: 66667 DEA: JMFPP EFIS: 0019000043 |
---|---|
DIST-CO-RTE-PM | 59--- |
Award Date | Not set |
Closeout Date | Not set |
Work Description | Special project for submitting Sample information for JMF Prequalification Program. |
Location Description | Not set |
QA Service Level | NOT VERIFIED |
Sample Information
Sample Taken Date | 01/17/2019 | Sample Unique Key | 11 |
---|---|---|---|
Will the laboratory/organization for which you are a member perform testing on this material sample? | No | Date that the sample was received by the laboratory/organization performing the testing | Not set |
Sample type | Quality Control | A brief description of the sample | 1/2" HMA-SP RAP WMA |
The quantity of what the sample constitutes | JMF | From where was the sample collected | Source |
First name of sampler or witnessed by | Marina | Last name of sampler or witnessed by | Kamel |
Title of sampler | Telephone number of sampler | 707-259-5708 | |
Laboratory sample identification | Linked DIME Sample ID | ||
The fabricator/manufacturer/facility name | Syar industry | Transportation Laboratory (TL) Number | |
Inspector Lot Number from the Transportation Laboratory (TL) Form | Structure unique identifier | Not set | |
Structure name | Not set |
Material Information
Material Type | Reclaimed Asphalt Pavement | RAP Source | Stockpile |
---|---|---|---|
Aggregate Size | Aggregate Source | ||
RAP Stockpile | Stockpile Size (tons) | ||
Reclaimed Asphalt Pavement Mix Number | Not set |
Test Details
DIME Sample ID: 2019-01-17-11
DIME Test ID: 2019-01-17-11-1
Testing Lab: CT HQ - Sacramento Hot Mix Asphalt Laboratory
Test Method: AASHTO T30-15: Standard Method of Test for Mechanical Analysis of Extracted Aggregate (Mechanical Analysis)
Test Release Date: 2019-04-05
Test Results
Input Type: Calculated
Tester's full name: Gurpartap Grewal
Date of test: 01/17/2019
Cumulative percent passing the 2 in. sieve: no data
Cumulative percent passing the 1 1/2 in. sieve: 100 %
Cumulative percent passing the 1 in. sieve: 100 %
Cumulative percent passing the 3/4 in. sieve: 100 %
Cumulative percent passing the 1/2 in. sieve: 100 %
Cumulative percent passing the 3/8 in. sieve: 99 %
Cumulative percent passing the 1/4 in. sieve: 99 %
Cumulative percent passing the #4 sieve: 82 %
Cumulative percent passing the #8 sieve: 63 %
Cumulative percent passing the #16 sieve: 49 %
Cumulative percent passing the #30 sieve: 38 %
Cumulative percent passing the #50 sieve: 28 %
Cumulative percent passing the #100 sieve: 18 %
Cumulative percent passing the #200 sieve: 12.2 %
General comments (publicly viewable) (Max 1000 characters): Rap Sample 3 T-30
Test was verified on 3/29/2019 ✔