Summary for Test 2023-10-17-3-2

Test performed: CTM 202-November 2011

Project Information

Project IdentifiersProject ID: 215420
DEA: 060R2104
EFIS: 0614000058
DIST-CO-RTE-PM06-MAD-41-6.2/9.2
Award Date01/18/2023
Closeout DateNot set
Work DescriptionFOR CONSTRUCTION ON STATE HIGHWAY IN MADERA COUNTY NEAR MADERA FROM 0.1 MILE NORTH OF AVENUE 15 TO 2.2 MILES NORTH OF FRIANT MADERA CANAL BRIDGE
Location DescriptionMADERA COUNTY NEAR MADERA FROM 0.1 MILE NORTH OF AVENUE 15 TO 2.2 MILES NORTH OF FRIANT MADERA CANAL BRIDGE
QA Service Level1 (Verified on 01/06/2021)

Sample Information

Sample Taken Date10/17/2023 Sample Unique Key3
Will the laboratory/organization for which you are a member perform testing on this material sample?Yes Date that the sample was received by the laboratory/organization performing the testing10/17/2023
Sample typeVerification A brief description of the sample1x4, 3/8, Sand
The quantity of what the sample constitutes0-100cy From where was the sample collectedManufacturer
First name of sampler or witnessed byNoah Last name of sampler or witnessed byHunt
Title of samplerSenior Materials Tester Telephone number of sampler
Laboratory sample identification Linked DIME Sample ID
The fabricator/manufacturer/facility nameBuilders Concrete Ready Mix Plant Sanger Transportation Laboratory (TL) Number
Inspector Lot Number from the Transportation Laboratory (TL) Form Structure unique identifier
Structure name

Material Information

Material TypeAggregate Source Identification (SMARA, name of Pit or Job Site)91-10-0010
The fabricator's/manufacturer's product name for the sample The fabricator/manufacturer designation for the sample
The plant number A detailed description of where the material sample was collectedBelt Cut at Plant
Where the material sample would have been placed if not sampled Primary Aggregate Nominal Size1 inch
The concrete mix design number Lot number
Sublot number Aggregate Mix Number

Test Details

DIME Sample ID: 2023-10-17-3
DIME Test ID: 2023-10-17-3-2
Testing Lab: CT D06 - Millbrook Field Laboratory
Test Method: CTM 202-November 2011: Method of Test for Sieve Analysis of Fine and Coarse Aggregates
Test Release Date: 2023-10-18

Test Results


What size aggregate is being tested?: Fine Aggregate
Individual or cumulative mass retained on each sieve?: Cumulative Mass Retained
For Combined Gradation only, has the fine aggregate sample been reduced?: No
For Combined Gradation only, use #40 Sieve?: No
Input Type: Calculated
Tester's full name: Tomas Silva
Date of test: 10/17/2023
Cumulative percent passing the 3/8 in. sieve: 100 %
Cumulative percent passing the #4 sieve: 97 %
Cumulative percent passing the #8 sieve: 82 %
Cumulative percent passing the #16 sieve: 67 %
Cumulative percent passing the #30 sieve: 45 %
Cumulative percent passing the #50 sieve: 20 %
Cumulative percent passing the #100 sieve: 7 %
Cumulative percent passing the #200 sieve: 4 %
General comments (publicly viewable) (Max 1000 characters):

Test was verified on 10/18/2023