Test 2021-08-20-54-3 (AASHTO T308-10) Summary

Project Information
Project IdentifiersProject ID: 214114
DEA: 040A5394
EFIS: 0418000244
DIST-CO-RTE-PM04-SOL-80,12-11.4/12.8, 2.1/2.8
Work DescriptionWiden EB SR-12 Connector, Construct 3 ramps & 2 box girder bridges, remove existing bridge, etc.
Location DescriptionI-80/I-680/Route 12 Interchange
Sample Information
Sample Taken Date8/20/2021 Sample Unique Key54
Will the laboratory/organization for which you are a member perform testing on this material sample?No Date that the sample was received by the laboratory/organization performing the testing8/20/2021
Sample typeVerification A brief description of the sample1 Bag of RAP Sampled pt e plant
The quantity of what the sample constitutes1 Bag RAP From where was the sample collectedManufacturer
First name of sampler or witnessed byIgnacio Last name of sampler or witnessed byArechiga
Title of sampler Laboratory sample identification
The fabricator/manufacturer/facility nameSYAR Lake Herman Drum Transportation Laboratory (TL) Number
Inspector Lot Number from the Transportation Laboratory (TL) Form Structure unique identifier
Structure name
Material Information
Material TypeReclaimed Asphalt Pavement RAP SourceLake Herman Quarry
Aggregate Size Aggregate Source
RAP Stockpile Stockpile Size (tons)
JMF Verification ID JMF3513-2021-80
Test Details
DIME Sample ID: 2021-08-20-54
DIME Test ID: 2021-08-20-54-3
Testing Lab: CT D04 - DME / District Lab
Test Method: AASHTO T308-10: Standard Method of Test for Determining the Asphalt Binder Content of Hot Mix Asphalt (HMA) by the Ignition Method (Asphalt Binder Content)
Test Release Date: 2021-09-22
Test Results

Input Type: Calculated
Tester's full name: XX
Date of test: 09/15/2021
Correction Factor (Percent by mass of HMA Specimen): no data %
Asphalt Binder Content:4.90 %
General comments (publicly viewable) (Max 1000 characters):

Test was verified on 09/22/2021