Test 2020-02-27-26-4 (AASHTO T269-14) Summary

Project Information
Project IdentifiersProject ID: 213411
DEA: 030H10U4
EFIS: 0317000246
DIST-CO-RTE-PM03-SAC-5-9.7/24.9
Work DescriptionNot set
Location DescriptionConstruction on state highway in Sacramento County in and near Sacramento from 1.1 miles south of Elk Grove Boulevard to American River Viaduct
Sample Information
Sample Taken Date2/27/2020 Sample Unique Key26
Will the laboratory/organization for which you are a member perform testing on this material sample?Yes Date that the sample was received by the laboratory/organization performing the testing2/28/2020
Sample typeVerification A brief description of the sample3/4" HMA - A, LL (Rich Bottom)
The quantity of what the sample constitutesJMF Verification From where was the sample collectedManufacturer
First name of sampler or witnessed byWalt Last name of sampler or witnessed byWylie (Witness)
Title of samplerTeichert Personnel Laboratory sample identificationJMF20-003
The fabricator/manufacturer/facility nameTeichert Perkins - Continuous Plant Transportation Laboratory (TL) Number
Inspector Lot Number from the Transportation Laboratory (TL) Form Structure unique identifier
Structure name
Material Information
Material TypeHot Mix Asphalt HMA TypeType A HMA
HMA Grading3/4 inch Lot number
Sublot number JMF Verification ID JMF3513-2020-231
Test Details
DIME Sample ID: 2020-02-27-26
DIME Test ID: 2020-02-27-26-4
Testing Lab: CT D03 - North Region Materials Lab
Test Method: AASHTO T269-14: Standard Method of Test for Percent Air Voids in Compacted Dense and Open Asphalt Mixtures (Air Void)
Test Release Date: 2020-12-24
Test Results

Number of tests: 3
Input Type: Calculated
Tester's full name: Jeff Herbert
Date of test: 03/23/2020
Percent Air Voids: 1.5 %
Percent Air Voids 2: 1.4
Percent Air Voids 3: 1.6
Percent Air Voids Average:1.5
General comments (publicly viewable) (Max 1000 characters): JMF20-003. Test date estimated.