Summary for Test 2020-04-29-8-1
Test performed: AASHTO T30-19Project Information
| Project Identifiers | Project ID: 99999 DEA: 0322222 |
|---|---|
| DIST-CO-RTE-PM | 03-SAC,OMG-888,99,80-0.6-0.6 |
| Award Date | Not set |
| Closeout Date | Not set |
| Work Description | THIS PROJECT RECORD WAS ADDED FOR DIME TESTERS - DATA SUBMITTED FOR THIS PROJECT SHOULD NOT BE USED FOR ANY OTHER PURPOSES. |
| Location Description | THIS PROJECT RECORD WAS ADDED FOR DIME TESTERS - DATA SUBMITTED FOR THIS PROJECT SHOULD NOT BE USED FOR ANY OTHER PURPOSES. |
| QA Service Level | (Verified on 04/05/2013) |
Sample Information
| Sample Taken Date | 04/29/2020 | Sample Unique Key | 8 |
|---|---|---|---|
| Will the laboratory/organization for which you are a member perform testing on this material sample? | Yes | Date that the sample was received by the laboratory/organization performing the testing | 04/29/2020 |
| Sample type | Verification | A brief description of the sample | RAp for Type A JMF |
| The quantity of what the sample constitutes | bag of RAP | From where was the sample collected | Source |
| First name of sampler or witnessed by | Clinton | Last name of sampler or witnessed by | Edmiston |
| Title of sampler | Telephone number of sampler | ||
| Laboratory sample identification | Linked DIME Sample ID | ||
| The fabricator/manufacturer/facility name | George Reed Plant | Transportation Laboratory (TL) Number | |
| Inspector Lot Number from the Transportation Laboratory (TL) Form | Structure unique identifier | ||
| Structure name | Bid Item | Not set |
Material Information
| Material Type | Reclaimed Asphalt Pavement | RAP Source | Plant |
|---|---|---|---|
| Aggregate Size | Unknown | Aggregate Source | Unknown |
| RAP Stockpile | Stockpile Size (tons) | Unknown | |
| Reclaimed Asphalt Pavement Mix Number | Not set |
Test Details
DIME Sample ID: 2020-04-29-8
DIME Test ID: 2020-04-29-8-1
Testing Lab: CT HQ - Sacramento Hot Mix Asphalt Laboratory
Test Method: AASHTO T30-19: Standard Method of Test for Mechanical Analysis of Extracted Aggregate (Mechanical Analysis)
Test Release Date: 2020-04-29
Test Results
Does this test use 1/4 sieve?: Yes
Is an aggregate correction factor used?: No
Input Type: Calculated
Tester's full name: John Doe
Date of test: 04/29/2020
| Cumulative Percent Passing | ||||||
|---|---|---|---|---|---|---|
| 100 % | ||||||
| 100 % | ||||||
| 100 % | ||||||
| 100 % | ||||||
| 100 % | ||||||
| 99.2 % | ||||||
| 99.2 % | ||||||
| 73.1 % | ||||||
| 53 % | ||||||
| 38.9 % | ||||||
| 27.6 % | ||||||
| 18.3 % | ||||||
| 12.2 % | ||||||
| 8.5 % | ||||||
General comments (publicly viewable) (Max 1000 characters):
Test was verified on 4/29/2020 ✔