Summary for Test 2025-09-17-22-4

Test performed: CTM 342-August 2012

Project Information

Project IdentifiersProject ID: 995125
DEA: 101E3004
EFIS: 1018000273
DIST-CO-RTE-PM10-SJ-5-32.5/49.8
Award Date01/12/2024
Closeout DateNot set
Work DescriptionREMOVE EXISTING PAVEMENT AND REPLACE WITH CONCRETE PAVEMENT.
Location DescriptionSAN JOAQUIN COUNTY IN AND NEAR STOCKTON FROM 0.2 MILE SOUTH OF HAMMER LANE UNDERCROSSING TO SACRAMENTO COUNTY LINE
QA Service Level1 (Verified on 09/26/2023)

Sample Information

Sample Taken Date09/17/2025 Sample Unique Key22
Will the laboratory/organization for which you are a member perform testing on this material sample?No Date that the sample was received by the laboratory/organization performing the testing09/17/2025
Sample typeAcceptance A brief description of the sampleCTM 342
The quantity of what the sample constitutesskid testing From where was the sample collectedJob Site
First name of sampler or witnessed byArmando Last name of sampler or witnessed byJose
Title of sampler Telephone number of sampler2096080054
Laboratory sample identification Linked DIME Sample ID
The fabricator/manufacturer/facility nameJOB SITES Transportation Laboratory (TL) Number
Inspector Lot Number from the Transportation Laboratory (TL) Form Structure unique identifier10-1E3004
Structure nameHwy 5 SB Stockton (8-Mile to Hammer Lane) Bid ItemNot set

Material Information

Material TypeRoadway/Bridge Surface Pavement Surface TypePCC (Portland Cement Concrete)
Type of Traffic Control ProvidedBehind K-Rail/Barrier DIST-CO-RTE10-SJ-5-32.5/49.8
Direction of TravelSouth Post Mile1976.00
Lanes to be TestedLane #1 Station

Test Details

DIME Sample ID: 2025-09-17-22
DIME Test ID: 2025-09-17-22-4
Testing Lab: CT HQ - FFS - Skid Testing
Test Method: CTM 342-August 2012: Method of Test for Surface Skid Resistance with the California Portable Skid Tester (Skid)
Test Release Date: 2025-09-30

Test Results


Pavement or Bridge Deck?: Pavement
Input Type: Measured
Tester's full name: Jessie Wilson
Date of test: 09/26/2025
Air Temperature: 74 F
Tire Pressure: 25 psi
Equipment PST #: 0835
Is Calibration within ± values: Yes
Weather: Sunny
Direction/Lane #: SB: Southbound Direction of Travel
Edge used to measure reference distance: Beginning of Construction (PM)
Edge used to measure position: Left of Right Construction Edge
Project Stationing 1: 337+97 ft
Project Stationing 2: 336+80 ft
Project Stationing 3: 335+51 ft
Project Stationing 4: 333+97 ft
Project Stationing 5: 332+62 ft
Direction and Lane # for Stationing 1: no data
Direction and Lane # for Stationing 2: no data
Direction and Lane # for Stationing 3: no data
Direction and Lane # for Stationing 4: no data
Direction and Lane # for Stationing 5: no data
Position for Stationing 1: 7 ft
Position for Stationing 2: 7 ft
Position for Stationing 3: 7 ft
Position for Stationing 4: 7 ft
Position for Stationing 5: 7 ft
Percent Grade for 1st Stationing: 0.0 %
Percent Grade for 2nd Stationing: -1.0 %
Percent Grade for 3rd Stationing: -1.0 %
Percent Grade for 4th Stationing: -1.0 %
Percent Grade for 5th Stationing: -1.0 %
Corrected Coefficients of Friction for Stationing 1: 0.46
Corrected Coefficients of Friction for Stationing 2: 0.46
Corrected Coefficients of Friction for Stationing 3: 0.46
Corrected Coefficients of Friction for Stationing 4: 0.46
Corrected Coefficients of Friction for Stationing 5: 0.46
Average Coefficient of Friction: 0.46
General comments (publicly viewable) (Max 1000 characters):

Test was verified on 9/30/2025