Summary for Test 2017-11-01-23-1

Test performed: AASHTO T30-15

Project Information

Project IdentifiersProject ID: 99999
DEA: 0322222
DIST-CO-RTE-PM03-SAC,OMG-888,99,80-0.6-0.6
Award DateNot set
Closeout DateNot set
Work DescriptionTHIS PROJECT RECORD WAS ADDED FOR DIME TESTERS - DATA SUBMITTED FOR THIS PROJECT SHOULD NOT BE USED FOR ANY OTHER PURPOSES.
Location DescriptionTHIS PROJECT RECORD WAS ADDED FOR DIME TESTERS - DATA SUBMITTED FOR THIS PROJECT SHOULD NOT BE USED FOR ANY OTHER PURPOSES.
QA Service Level (Verified on 04/05/2013)

Sample Information

Sample Taken Date11/01/2017 Sample Unique Key23
Will the laboratory/organization for which you are a member perform testing on this material sample?No Date that the sample was received by the laboratory/organization performing the testingNot set
Sample typeQuality Control A brief description of the sampleRAP ignition 3
The quantity of what the sample constitutes1 From where was the sample collectedSource
First name of sampler or witnessed byDime Last name of sampler or witnessed byTest
Title of sampler Telephone number of sampler
Laboratory sample identification Linked DIME Sample ID
The fabricator/manufacturer/facility nameTest Transportation Laboratory (TL) Number
Inspector Lot Number from the Transportation Laboratory (TL) Form Structure unique identifierNot set
Structure nameNot set

Material Information

Material TypeReclaimed Asphalt Pavement RAP SourceMustang Pit
Aggregate SizeNot set Aggregate SourceNot set
RAP StockpileNot set Stockpile Size (tons)Not set
Reclaimed Asphalt Pavement Mix NumberNot set

Test Details

DIME Sample ID: 2017-11-01-23
DIME Test ID: 2017-11-01-23-1
Testing Lab: CT HQ - Sacramento Materials Management Branch Field Office
Test Method: AASHTO T30-15: Standard Method of Test for Mechanical Analysis of Extracted Aggregate (Mechanical Analysis)
Test Release Date: 2017-11-03

Test Results


Input Type: Calculated
Tester's full name: David Phong
Date of test: 11/03/2017
Cumulative percent passing the 2 in. sieve: no data
Cumulative percent passing the 1 1/2 in. sieve: 100 %
Cumulative percent passing the 1 in. sieve: 100 %
Cumulative percent passing the 3/4 in. sieve: 100 %
Cumulative percent passing the 1/2 in. sieve: 99.9 %
Cumulative percent passing the 3/8 in. sieve: 94.9 %
Cumulative percent passing the 1/4 in. sieve: 68.4 %
Cumulative percent passing the #4 sieve: 49.7 %
Cumulative percent passing the #8 sieve: 45.9 %
Cumulative percent passing the #16 sieve: 37.6 %
Cumulative percent passing the #30 sieve: 29.1 %
Cumulative percent passing the #50 sieve: 21.7 %
Cumulative percent passing the #100 sieve: 15.5 %
Cumulative percent passing the #200 sieve: 10.9 %
General comments (publicly viewable) (Max 1000 characters):

Test was verified on 11/3/2017