Summary for Test 2025-04-22-109-2
Test performed: ASTM D5329-16Project Information
| Project Identifiers | Project ID: 66669 DEA: JMF-DATA EFIS: JMF-DATA |
|---|---|
| DIST-CO-RTE-PM | 59--- |
| Award Date | Not set |
| Closeout Date | Not set |
| Work Description | Special project for storing JMF sample data |
| Location Description | Not set |
| QA Service Level | NOT VERIFIED |
Sample Information
| Sample Taken Date | 04/22/2025 | Sample Unique Key | 109 |
|---|---|---|---|
| Will the laboratory/organization for which you are a member perform testing on this material sample? | Yes | Date that the sample was received by the laboratory/organization performing the testing | 05/12/2025 |
| Sample type | Verification | A brief description of the sample | Asphalt Rubber Binder (PG 64-16 CR) |
| The quantity of what the sample constitutes | Production Start-Up Evaluation/JMF Vericfication | From where was the sample collected | Manufacturer |
| First name of sampler or witnessed by | Ward | Last name of sampler or witnessed by | Jenkins |
| Title of sampler | Not set | Telephone number of sampler | Not set |
| Laboratory sample identification | Not set | Linked DIME Sample ID | Not set |
| The fabricator/manufacturer/facility name | Mercer-Fraser Company — Boyd Road Plant (Arcata, CA) | Transportation Laboratory (TL) Number | Not set |
| Inspector Lot Number from the Transportation Laboratory (TL) Form | Structure unique identifier | Not set | |
| Structure name | Not set | Bid Item | Not set |
Material Information
| Material Type | Asphalt Rubber Binder | Asphalt modifier supplier | Not set |
|---|---|---|---|
| Performance Grade | PG 64-16 | Lot number | Not set |
| Sublot number | Not set | Asphalt Rubber Binder Mix Number | Not set |
Test Details
DIME Sample ID: 2025-04-22-109
DIME Test ID: 2025-04-22-109-2
Testing Lab: CT D02 - Redding Northern Regional Laboratory
Test Method: ASTM D5329-16: Standard Test Methods for Sealants and Fillers, Hot-Applied, for Joints and Cracks in Asphalt Pavements and Portland Cement Concrete Pavements (Asphalt Pavement)
Test Release Date: 2025-06-11
Test Results
Input Type: Calculated
Tester's full name: Glenn Bradley
Date of test: 05/22/2025
Temperature: no data
Ball Penetration (P1): no data
Final Dial reading (F1): no data
Ball Penetration (P2): no data
Final Dial reading (F2): no data
Ball Penetration (P3): no data
Final Dial reading (F3): no data
Resilience 1: no data
Resilience 2: no data
Resilience 3: no data
Average Resilience: 38 %
Minutes Reaction: no data
General comments (publicly viewable) (Max 1000 characters): Submitted from JMF - Ward Jenkins
Test was verified on 6/11/2025 ✔