Summary for Test 2023-11-30-34-6

Test performed: AASHTO T27-14

Project Information

Project IdentifiersProject ID: 994803
DEA: 043J0704
EFIS: 0415000077
DIST-CO-RTE-PM04-CC-80-10.1/13.5
Award Date03/10/2023
Closeout DateNot set
Work DescriptionRemove PCC and AC, place PCP and AC Resurfacing.
Location DescriptionConstruction on State Highway in Contra Costa County in Hercules and Crockett from Route 80/4 separation to 0.1 mile west of Crockett Viaduct.
QA Service Level1 (Verified on 05/10/2023)

Sample Information

Sample Taken Date11/30/2023 Sample Unique Key34
Will the laboratory/organization for which you are a member perform testing on this material sample?Yes Date that the sample was received by the laboratory/organization performing the testing12/04/2023
Sample typeQuality Assurance A brief description of the sample1/2-INCH HMA-SP Type A
The quantity of what the sample constitutesLOT 3 SUBLOT 5 From where was the sample collectedSource
First name of sampler or witnessed byIGNACIO Last name of sampler or witnessed byARECHIGA
Title of sampler Telephone number of sampler5102077252
Laboratory sample identification Linked DIME Sample ID
The fabricator/manufacturer/facility nameCounty Asphalt Batch Plant Transportation Laboratory (TL) Number
Inspector Lot Number from the Transportation Laboratory (TL) Form Structure unique identifier
Structure name

Material Information

Material TypeAggregate Source Identification (SMARA, name of Pit or Job Site)91-07-0003
The fabricator's/manufacturer's product name for the sample The fabricator/manufacturer designation for the sample
The plant number A detailed description of where the material sample was collectedSample Pick-Up From Plant
Where the material sample would have been placed if not sampled Primary Aggregate Nominal Size1/2 inch
The concrete mix design number Lot number3
Sublot number5 Aggregate Mix NumberL230620

Test Details

DIME Sample ID: 2023-11-30-34
DIME Test ID: 2023-11-30-34-6
Testing Lab: CT D04 - Richmond Field Laboratory
Test Method: AASHTO T27-14: Standard Method of Test for Sieve Analysis of Fine and Coarse Aggregates (Sieve Analysis)
Test Release Date: 2023-12-05

Test Results


What type of gradation is being tested?: Combined Gradation
Individual or cumulative mass retained on each sieve?: Cumulative Mass Retained
Does this test use 1/4 sieve? (question for HMA Gradation Type): No
Has the fine aggregate sample been reduced?: Yes
Input Type: Calculated
Tester's full name: IGNACIO ARECHIGA
Date of test: 12/04/2023
Cumulative percent passing the 2 in. sieve: 0 %
Cumulative percent passing the 1 1/2 in. sieve: 0 %
Cumulative percent passing the 1 in. sieve: 100 %
Cumulative percent passing the 3/4 in. sieve: 100 %
Cumulative percent passing the 1/2 in. sieve: 96 %
Cumulative percent passing the 3/8 in. sieve: 87 %
Cumulative percent passing the #4 sieve: 60 %
Cumulative percent passing the #8 sieve: 35 %
Cumulative percent passing the #16 sieve: 21 %
Cumulative percent passing the #30 sieve: 13 %
Cumulative percent passing the #50 sieve: 8 %
Cumulative percent passing the #100 sieve: 4 %
Cumulative percent passing the #200 sieve: 2.9 %
General comments (publicly viewable) (Max 1000 characters): LOT 3 SUBLOT 5 County Asphalt Batch Plant Sieve 4 FAILED