Summary for Test 2021-01-10-5-2

Test performed: AASHTO T269-14

Project Information

Project IdentifiersProject ID: 66667
DEA: JMFPP
EFIS: 0019000043
DIST-CO-RTE-PM59---
Award DateNot set
Closeout DateNot set
Work DescriptionSpecial project for submitting Sample information for JMF Prequalification Program.
Location DescriptionNot set
QA Service LevelNOT VERIFIED

Sample Information

Sample Taken Date01/10/2021 Sample Unique Key5
Will the laboratory/organization for which you are a member perform testing on this material sample?Yes Date that the sample was received by the laboratory/organization performing the testing01/10/2021
Sample typePreliminary A brief description of the sample3/4" HMA-SP WMA
The quantity of what the sample constitutes780 Pounds From where was the sample collectedManufacturer
First name of sampler or witnessed byCody Last name of sampler or witnessed byBrown
Title of sampler Telephone number of sampler
Laboratory sample identification Linked DIME Sample ID
The fabricator/manufacturer/facility nameSyar Todd Road Batch Transportation Laboratory (TL) Number
Inspector Lot Number from the Transportation Laboratory (TL) Form Structure unique identifier
Structure name

Material Information

Material TypeHot Mix Asphalt HMA TypeType A HMA
HMA Grading3/4 inch Lot number
Sublot number HMA Mix NumberNot set

Test Details

DIME Sample ID: 2021-01-10-5
DIME Test ID: 2021-01-10-5-2
Testing Lab: Syar Industries, Incorporated
Test Method: AASHTO T269-14: Standard Method of Test for Percent Air Voids in Compacted Dense and Open Asphalt Mixtures (Air Void)
Test Release Date: 2021-03-18

Test Results


Number of tests: 3
Is the sample lab compacted or field compacted?:
Input Type: Calculated
Tester's full name: Cody Brown
Date of test: 01/10/2021
Percent Air Voids: 4 %
Percent Air Voids 2: 3.9 %
Percent Air Voids 3: 4.1 %
Average Percent Air Voids: 4 %
General comments (publicly viewable) (Max 1000 characters):

Test was verified on 3/18/2021