Sample Record

DIME Sample ID 2024-04-18-82

Project Information

Project IdentifiersProject ID: 215425
DEA: 06360244
EFIS: 0613000005
DIST-CO-RTE-PM06-TUL-99-30.6/35.2
Award Date04/26/2021
Closeout Date08/31/2026
Work DescriptionWiden Freeway & Bridge Construction (Concrete Bridge)
Location DescriptionNot set
QA Service Level1 (Verified on 11/01/2021)

Owner Lab

  • G3 Quality, Incorporated - Cerritos

Sample Information

Sample Taken Date04/18/2024 Sample Unique Key82
Date that the sample was received by the laboratory/organization performing the testing04/19/2024 Sample typeQuality Control
A brief description of the sample1", 3/8", WCS The quantity of what the sample constitutes1 Bag
From where was the sample collectedJob Site First name of sampler or witnessed byAl
Last name of sampler or witnessed byPineda Title of samplerQC Field Technician
Telephone number of sampler Laboratory sample identificationMix G3-22-BAR-318, Set 1
Linked DIME Sample IDUnknown The fabricator/manufacturer/facility nameSecurity Paving - Sanger
Transportation Laboratory (TL) NumberUnknown Inspector Lot Number from the Transportation Laboratory (TL) FormUnknown
Structure unique identifier00-0000 Structure name
Bid ItemNot set

Material Information

Material TypeAggregate Source Identification (SMARA, name of Pit or Job Site)91-10-0010
The fabricator's/manufacturer's product name for the sampleSet 1 The fabricator/manufacturer designation for the sampleUnknown
The plant numberUnknown A detailed description of where the material sample was collectedBelt Cut
Where the material sample would have been placed if not sampledUnknown Primary Aggregate Nominal Size1 inch
The concrete mix design numberG3-22-BAR-318 Lot number1
Sublot number1 Aggregate Mix Number

Submitted Tests

DIME Test IDTest MethodTester Name, Testing LabDate TestedDate AddedVerified?Release DateTest CommentsPrivacy LevelActions
No results found.

Sample File Attachments

File NameExtensionDate UploadedActions
No results found.

Test File Attachments