Sample Record

Owner Lab

  • CT D05 - Carpinteria Field Laboratory

DIME Sample ID 2023-01-12-57

Project Information

Project IdentifiersProject ID: 994087
DEA: 051G4104
EFIS: 0515000012
DIST-CO-RTE-PM05-SB-101-4.0/4.8
Award Date09/02/2022
Closeout Date08/12/2024
Work DescriptionSanta Claus Lane Bike Path - !!Charge time to 05-0N72U4 per Project Manager / Corridor Manager!!
Location Description!!Charge time to 05-0N72U4 per Project Manager / Corridor Manager!!
QA Service Level1 (Verified on 07/25/2022)

Sample Information

Sample Taken Date01/12/2023 Sample Unique Key57
Will the laboratory/organization for which you are a member perform testing on this material sample?Yes Date that the sample was received by the laboratory/organization performing the testing01/12/2023
Sample typeQuality Assurance A brief description of the sampleConcrete Sample
The quantity of what the sample constitutes19 cy From where was the sample collectedJob Site
First name of sampler or witnessed byDorell Last name of sampler or witnessed byHarper
Title of sampler Telephone number of sampler6692889248
Laboratory sample identification Linked DIME Sample ID
The fabricator/manufacturer/facility nameMartin Marietta Goleta Transportation Laboratory (TL) Number
Inspector Lot Number from the Transportation Laboratory (TL) Form Structure unique identifier
Structure name Bid ItemNot set

Material Information

Material TypeConcrete The concrete mix design number725A1Z0P
The truck number from where the sample was collected545D The batch plant ticket number from where the sample was collected3432677
Concrete batch plant The fabricator/manufacturer designation for the sample
A detailed description of where the material sample was collectedDischarge from concrete truck into wheelbarrow. Where the material sample would have been placed if not sampled
From Lot No. Bag Lot No.

Submitted Tests

DIME Test IDTest MethodTester Name, Testing LabDate TestedDate AddedVerified?Release DateTest CommentsPrivacy LevelActions
2023-01-12-57-1CTM 521-June 2020: Method of Test for Compressive Strength of Molded Concrete CylindersJesse Gomez, CT D05 - Carpinteria Field Laboratory02/09/202302/17/2023
Yes
02/17/20234x8 cylinders broken todayPublic - Test Data Visible
2023-01-12-57-2CTM 557-June 2020: Method of Test for Temperature of Freshly Mixed Hydraulic Cement ConcreteJesse Gomez, CT D05 - Carpinteria Field Laboratory01/12/202302/17/2023
Yes
02/17/2023conc. temp takenPublic - Test Data Visible
2023-01-12-57-3ASTM C143-15a: Standard Test Method for Slump of Hydraulic-Cement ConcreteJesse Gomez, CT D05 - Carpinteria Field Laboratory01/12/202302/17/2023
Yes
02/17/2023slump takenPublic - Test Data Visible

Sample File Attachments

File NameExtensionDate UploadedActions
No results found.

Test File Attachments


DIME Test ID: 2023-01-12-57-1 CTM 521-June 2020 (Verified)
DIME Test ID: 2023-01-12-57-2 CTM 557-June 2020 (Verified)
DIME Test ID: 2023-01-12-57-3 ASTM C143-15a (Verified)