Sample Record

Owner Lab

  • CT D07 - Materials Field Laboratory, Unit 1953

DIME Sample ID 2022-04-24-7

Project Information

Project IdentifiersProject ID: 214493
DEA: 07311704
EFIS: 0715000013
DIST-CO-RTE-PM07-LA-134-0.0/R13.3
Award Date04/16/2020
Closeout Date07/09/2024
Work DescriptionCONCRETE SLAB REPLACEMENT, HMA PAVING, ELECTRICAL AND LANDSCAPE WORK.
Location DescriptionLOS ANGELES COUNTY IN LOS ANGELES, BURBANK, GLENDALE AND PASADENA FROM ROUTE 101/134 SEPARATION TO JUNCTION OF ROUTE 210/710
QA Service Level1 (Verified on 04/15/2020)

Sample Information

Sample Taken Date04/24/2022 Sample Unique Key7
Will the laboratory/organization for which you are a member perform testing on this material sample?Yes Date that the sample was received by the laboratory/organization performing the testing04/24/2022
Sample typeDepartment Acceptance A brief description of the sampleConcrete slab replacement
The quantity of what the sample constitutes+/- 200 CY From where was the sample collectedJob Site
First name of sampler or witnessed byRobert Last name of sampler or witnessed byAchuela
Title of samplerMREA Telephone number of sampler
Laboratory sample identification22-0911 Linked DIME Sample ID
The fabricator/manufacturer/facility namePeterson Chase Transportation Laboratory (TL) NumberNA
Inspector Lot Number from the Transportation Laboratory (TL) Form Structure unique identifier
Structure name Bid ItemNot set

Material Information

Material TypeConcrete The concrete mix design numberNA
The truck number from where the sample was collected2122 The batch plant ticket number from where the sample was collectedNA
Concrete batch plantNA The fabricator/manufacturer designation for the sample
A detailed description of where the material sample was collectedtruck chute Where the material sample would have been placed if not sampledNA
From Lot No. Bag Lot No.

Submitted Tests

DIME Test IDTest MethodTester Name, Testing LabDate TestedDate AddedVerified?Release DateTest CommentsPrivacy LevelActions
2022-04-24-7-1CTM 524-March 2013: Method of Test for Flexural Strength Of Rapid Strength ConcreteRobert Achuela, CT D07 - Materials Field Laboratory, Unit 195304/27/202204/27/2022
Yes
04/27/2022Public - Test Data Visible

Sample File Attachments

File NameExtensionDate UploadedActions
No results found.

Test File Attachments


DIME Test ID: 2022-04-24-7-1 CTM 524-March 2013 (Verified)