Sample Record

DIME Sample ID 2022-04-13-35

Project Information

Project IdentifiersProject ID: 214451
DEA: 07303704
EFIS: 0714000035
DIST-CO-RTE-PM07-LA-101-8.0/27.3
Award Date12/19/2019
Closeout Date05/07/2024
Work DescriptionREPLACE CONCRETE BARRIERS.
Location DescriptionTHE CITY AND COUNTY OF LOS ANGELES FROM PILGRIMAGE OVERCROSSING TO VALLEY CIRCLE BOULEVARD OVERCROSSING
QA Service Level1 (Verified on 08/12/2020)

Owner Lab

  • CT D07 - Materials Field Laboratory, Unit 1953

Sample Information

Sample Taken Date04/13/2022 Sample Unique Key35
Date that the sample was received by the laboratory/organization performing the testing04/14/2022 Sample typeDepartment Acceptance
A brief description of the sample6x12 LCB cylinders The quantity of what the sample constitutes10 yd3
From where was the sample collectedJob Site First name of sampler or witnessed byRosauro
Last name of sampler or witnessed byNogoy Title of samplerTEC
Telephone number of sampler2137939321 Laboratory sample identification22-0792
Linked DIME Sample ID The fabricator/manufacturer/facility nameNational Ready Mix Concrete Company
Transportation Laboratory (TL) Number Inspector Lot Number from the Transportation Laboratory (TL) Form
Structure unique identifier Structure name
Bid ItemNot set

Material Information

Material TypeConcrete The concrete mix design numberS29000
The truck number from where the sample was collected3 The batch plant ticket number from where the sample was collected480200
Concrete batch plant The fabricator/manufacturer designation for the sample
A detailed description of where the material sample was collectedChute discharge into wheel barrow Where the material sample would have been placed if not sampled
From Lot No. Bag Lot No.

Submitted Tests

DIME Test IDTest MethodTester Name, Testing LabDate TestedDate AddedVerified?Release DateTest CommentsPrivacy LevelActions
No results found.

Sample File Attachments

File NameExtensionDate UploadedActions
No results found.

Test File Attachments