Sample Record

DIME Sample ID 2022-04-14-5

Sample is locked from editing. info

Project Information

Project IdentifiersProject ID: 214579
DEA: 010B0904
EFIS: 0100020444
DIST-CO-RTE-PM01-DN-101-8.2/8.7
Award Date04/21/2020
Closeout Date12/02/2025
Work DescriptionPanther Creek & Hunter Creek Bridges
Location DescriptionDEL NORTE COUNTY NEAR KLAMATH AT PANTHER CREEK BRIDGE AND AT HUNTER CREEK BRIDGE
QA Service Level1 (Verified on 03/02/2020)

Owner Lab

  • CT HQ - QASI Bay Area Field Office

Sample Information

Sample Taken Date04/14/2022 Sample Unique Key5
Date that the sample was received by the laboratory/organization performing the testing04/18/2022 Sample typeQuality Assurance
A brief description of the sample#4 dayton 101/101A couplers The quantity of what the sample constitutes50 pieces
From where was the sample collectedFabricator First name of sampler or witnessed byGreg
Last name of sampler or witnessed byThompson Title of samplerAssociate Steel Inspector
Telephone number of sampler510-376-7155 cell Laboratory sample identification
Linked DIME Sample ID The fabricator/manufacturer/facility namePJ's rebar
Transportation Laboratory (TL) Number Inspector Lot Number from the Transportation Laboratory (TL) FormB9-052-22
Structure unique identifier Structure namePanther Creek
Bid ItemNot set

Material Information

Material TypeSMTL TM5 - Couplers Production or Authorization TestingProduction Testing
Service or UltimateService Material Standard CodeASTM A706
Material Grade60 Rebar ManufacturerNucor
Coupler ManufacturerDayton Intermediate Assembler or FabricatorPJ rebar
Rebar Size#4 Coupler ModelD101/101A
Coating StandardsUncoated Shape of RebarStraight
Rebar Hoop Diameter Rebar Hoop Fabricator
Coupler Component Heat/Lot Number(s)N/A Rebar Heat Number(s)3500021186
Rebar Size 2 4 Coupler Unique IDNot set

Submitted Tests

DIME Test IDTest MethodTester Name, Testing LabDate TestedDate AddedVerified?Release DateTest CommentsPrivacy LevelActions
2022-04-14-5-2CTM 670-December 2013: Method of Tests for Mechanical and Welded Reinforcing Steel Splices (Cyclical/Fatique Tensile with Slip)bewing, CT HQ - Sacramento Structural Materials Testing Laboratory04/21/202204/21/2022
Yes
04/21/2022Ok NeckingPublic - Test Data Visible
2022-04-14-5-3CTM 670-December 2013: Method of Tests for Mechanical and Welded Reinforcing Steel Splices (Cyclical/Fatique Tensile with Slip)bewing, CT HQ - Sacramento Structural Materials Testing Laboratory04/21/202204/21/2022
Yes
04/21/2022Ok NeckingPublic - Test Data Visible
2022-04-14-5-4CTM 670-December 2013: Method of Tests for Mechanical and Welded Reinforcing Steel Splices (Cyclical/Fatique Tensile with Slip)bewing, CT HQ - Sacramento Structural Materials Testing Laboratory04/21/202204/21/2022
Yes
04/21/2022Ok NeckingPublic - Test Data Visible

Sample File Attachments

File NameExtensionDate UploadedActions
No results found.

Test File Attachments


DIME Test ID: 2022-04-14-5-2 CTM 670-December 2013 (Verified)
DIME Test ID: 2022-04-14-5-3 CTM 670-December 2013 (Verified)
DIME Test ID: 2022-04-14-5-4 CTM 670-December 2013 (Verified)