Sample Record

DIME Sample ID 2026-02-13-23

Project Information

Project IdentifiersProject ID: 1001375
DEA: 040A53T4
EFIS: 0421000155
COOP: 040A53TCM
DIST-CO-RTE-PM04-SOL-80-L1.8/L3.2
Award Date06/20/2025
Closeout DateNot set
Work DescriptionConstruct I-80 WB Truck Scales
Location DescriptionCONSTRUCTION ON STATE HIGHWAY IN SOLANO COUNTY IN AND NEAR FAIRFIELD ON ROUTE 12 FROM THE 80/12 EAST JUNCTION TO 0.9 MILE EAST OF CHADBOURNE ROAD UNDERCROSSING AND ON ROUTE 80 FROM 0.5 MILE WEST OF DAN WILSON CREEK BRIDGE TO WEST TEXAS STREET UNDERCROSSI
QA Service Level1 (Verified on 07/10/2025)

Owner Lab

  • CT D04 - Concord Field Laboratory

Sample Information

Sample Taken Date02/13/2026 Sample Unique Key23
Date that the sample was received by the laboratory/organization performing the testingNot set Sample typePreliminary
A brief description of the sampleNative Borrow The quantity of what the sample constitutes2 Bags
From where was the sample collectedJob Site First name of sampler or witnessed byChristian
Last name of sampler or witnessed bySousa Title of sampler
Telephone number of sampler Laboratory sample identification
Linked DIME Sample ID The fabricator/manufacturer/facility nameKiewit Infrastructure West
Transportation Laboratory (TL) Number Inspector Lot Number from the Transportation Laboratory (TL) Form
Structure unique identifier Structure name
Bid ItemNot set

Material Information

Material TypeSoil The fabricator's/manufacturer's product name for the sample
The fabricator/manufacturer designation for the sample A detailed description of where the material sample was collectedStockpile @ Jobsite
Where the material sample would have been placed if not sampled

Submitted Tests

DIME Test IDTest MethodTester Name, Testing LabDate TestedDate AddedVerified?Release DateTest CommentsPrivacy LevelActions
No results found.

Sample File Attachments

File NameExtensionDate UploadedActions
No results found.

Test File Attachments