Sample Record
Owner Lab
- CT D06 - Bakersfield Field Laboratory
DIME Sample ID 2024-11-03-12
Sample is locked from editing. info
Project Information
Project Identifiers | Project ID: 994976 DEA: 060X3304 EFIS: 0618000055 |
---|---|
DIST-CO-RTE-PM | 06-KER-5-R0.0/4.4 |
Award Date | 10/23/2023 |
Closeout Date | Not set |
Work Description | REPLACE ROADWAY PAVEMENT WITH HMA AND CONCRETE. |
Location Description | KERN COUNTY AT AND NEAR LEBEC FROM LOS ANGELES COUNTY LINE TO GRAPEVINE CREEK |
QA Service Level | 1 (Verified on 07/27/2023) |
Sample Information
Sample Taken Date | 11/03/2024 | Sample Unique Key | 12 |
---|---|---|---|
Will the laboratory/organization for which you are a member perform testing on this material sample? | Yes | Date that the sample was received by the laboratory/organization performing the testing | 11/05/2024 |
Sample type | Acceptance | A brief description of the sample | JPCP- cylinders |
The quantity of what the sample constitutes | 0-300CY | From where was the sample collected | Job Site |
First name of sampler or witnessed by | Neale | Last name of sampler or witnessed by | Brown |
Title of sampler | Telephone number of sampler | ||
Laboratory sample identification | Linked DIME Sample ID | ||
The fabricator/manufacturer/facility name | SPCI onsite | Transportation Laboratory (TL) Number | |
Inspector Lot Number from the Transportation Laboratory (TL) Form | Structure unique identifier | ||
Structure name |
Material Information
Material Type | Concrete | The concrete mix design number | G3-18-PCC-128R |
---|---|---|---|
The truck number from where the sample was collected | The batch plant ticket number from where the sample was collected | 1 | |
Concrete batch plant | The fabricator/manufacturer designation for the sample | ||
A detailed description of where the material sample was collected | Back of Truck | Where the material sample would have been placed if not sampled | |
From Lot No. | Bag Lot No. |
Submitted Tests
Sample File Attachments
File Name | Extension | Date Uploaded | Actions |
---|---|---|---|
No results found. |
Test File Attachments
DIME Test ID: 2024-11-03-12-1 CTM 521-June 2020 (Verified)
File Name | Extension | Date Uploaded | Test ID | Actions |
---|---|---|---|---|
06-0X3304_37049_241104_23_42D | 12/16/2024 | 2024-11-03-12-1 | Info |