Sample Record

Owner Lab

  • CT D06 - Millbrook Field Laboratory

DIME Sample ID 2024-11-05-5

Sample is locked from editing. info

Project Information

Project IdentifiersProject ID: 993141
DEA: 060V1204
EFIS: 0616000207
DIST-CO-RTE-PM06-MAD-99-R6.9/R7.6
Award Date06/22/2022
Closeout DateNot set
Work DescriptionCottonwood Creek Bridge Replacement - REPLACE BRIDGES AND CONSTRUCT RETAINING WALLS.
Location DescriptionMADERA COUNTY NEAR MADERA FROM 0.4 MILE SOUTH OF COTTONWOOD CREEK BRIDGE TO 0.1 MILE NORTH OF AVENUE 12 OVERCROSSING
QA Service Level1 (Verified on 07/28/2021)

Sample Information

Sample Taken Date11/05/2024 Sample Unique Key5
Will the laboratory/organization for which you are a member perform testing on this material sample?Yes Date that the sample was received by the laboratory/organization performing the testing11/06/2024
Sample typeQuality Assurance A brief description of the sampleBackwall concrete
The quantity of what the sample constitutes11 cy From where was the sample collectedJob Site
First name of sampler or witnessed byAdam Last name of sampler or witnessed byMahmoud
Title of sampler Telephone number of sampler
Laboratory sample identification Linked DIME Sample ID
The fabricator/manufacturer/facility nameBuilders Transportation Laboratory (TL) Number
Inspector Lot Number from the Transportation Laboratory (TL) Form Structure unique identifier
Structure name

Material Information

Material TypeConcrete The concrete mix design numberND22023
The truck number from where the sample was collected9109 The batch plant ticket number from where the sample was collected1366547
Concrete batch plant111 The fabricator/manufacturer designation for the sample
A detailed description of where the material sample was collectedLoader bucket Where the material sample would have been placed if not sampled
From Lot No. Bag Lot No.

Submitted Tests

DIME Test IDTest MethodTester Name, Testing LabDate TestedSubmitted ByVerified?Release DateTest CommentsActions
2024-11-05-5-1CTM 521-June 2020: Method of Test for Compressive Strength of Molded Concrete CylindersGurjeet Litt, CT D06 - Millbrook Field Laboratory12/03/2024Gurjeet Litt
Yes
12/03/2024Required strength 4000 psi @ 28 days

Sample File Attachments

File NameExtensionDate UploadedActions
No results found.

Test File Attachments


DIME Test ID: 2024-11-05-5-1 CTM 521-June 2020 (Verified)