Project Details
This page displays current information for project DEA: 120U6104.
Project Information
Project Identifiers | Project ID: 994357 DEA: 120U6104 EFIS: 1223000043 |
---|---|
DIST-CO-RTE-PM | 12-ORA-1-12.07/12.08 |
Award Date | 10/03/2022 |
Closeout Date | Not set |
Work Description | Construct soldier pile wall with pre-cast concrete lagging to retain cement slurry backfill placed in gully within Caltrans' Right of Way. Replaced damaged drainage system including down pipe. Install new guardrail system. |
Location Description | Route 1 Shoulder |
QA Service Level | 1 (Verified on 07/07/2023) |
Caltrans Project Personnel
Personnel stored in Caltrans' project databases.
Email Address | Full Name | Role | Personnel Source |
---|---|---|---|
james.devey@dot.ca.gov | James Devey | METS REP | Caltrans METS REP DB |
Samples
Samples submitted for this project.
DIME Sample ID | Sample Taken Date | Sample Received Date | Sample Type | Material Type | Link |
---|---|---|---|---|---|
No results found. |
Job Mix Formula (JMF)
JMFs associated with this project.
JMF ID | Status | Submitted By | Created By | Date Created | Link |
---|---|---|---|---|---|
No results found. |
Environmental Product Declaration (EPD)
EPDs material quantities submitted for this project.
Declaration Number | Material Type | Vendor | Submitted by | Quantity |
---|---|---|---|---|
No results found. |
Project Summary Graphs
Samples Taken and Tests performed per Month
Number of Samples
Sample Types
Number of Tests
Test Types
Material Types
Test Methods