Project Details
This page displays current information for project DEA: 043Y5504.
Project Information
| Project Identifiers | Project ID: 994662 DEA: 043Y5504 EFIS: 0423000260 |
|---|---|
| DIST-CO-RTE-PM | 04-ALA,ALA-580-4.7/4.8 |
| Award Date | Not set |
| Closeout Date | Not set |
| Work Description | RETAINING WALL OVERTURNING FAILURE |
| Location Description | Not set |
| QA Service Level | 1 (Verified on 04/11/2023) |
Caltrans Project Personnel
Personnel stored in Caltrans' project databases.
| Email Address | Full Name | Role | Personnel Source |
|---|---|---|---|
| paramjit.pandher@dot.ca.gov | Paramjit Pandher | Resident Engineer | Caltrans RE DB |
| john.parecadan@dot.ca.gov | John K. Parecadan | Structural Representative | Caltrans SR DB |
| dylan.larose@dot.ca.gov | Dylan Larose | METS REP | Caltrans METS REP DB |
Samples
Samples submitted for this project.
Displaying 1-10 of 13 results.
| DIME Sample ID | Sample Taken Date | Sample Received Date | Sample Type | Material Type | Link |
|---|---|---|---|---|---|
| 2025-05-19-120 | 05/19/2025 | 05/27/2025 | Production Start-Up | Aggregate | View |
| 2025-05-29-25 | 05/29/2025 | 05/30/2025 | Quality Assurance | Hot Mix Asphalt | View |
| 2025-05-28-39 | 05/28/2025 | 05/29/2025 | Quality Assurance | Hot Mix Asphalt | View |
| 2025-05-27-27 | 05/27/2025 | 05/28/2025 | Quality Assurance | Hot Mix Asphalt | View |
| 2025-05-29-24 | 05/29/2025 | 05/30/2025 | Quality Assurance | Aggregate | View |
| 2025-05-28-20 | 05/28/2025 | 05/29/2025 | Quality Assurance | Aggregate | View |
| 2025-05-21-60 | 05/21/2025 | 05/22/2025 | Quality Assurance | Hot Mix Asphalt | View |
| 2025-05-27-13 | 05/27/2025 | 05/28/2025 | Quality Assurance | Aggregate | View |
| 2025-05-21-30 | 05/21/2025 | 05/22/2025 | Quality Assurance | Aggregate | View |
| 2025-05-20-42 | 05/20/2025 | 05/21/2025 | Quality Assurance | Aggregate | View |
Job Mix Formula (JMF)
JMFs associated with this project.
| JMF ID | Status | Submitted By | Created By | Date Created | Link |
|---|---|---|---|---|---|
| No results found. | |||||
Precast Concrete Forms
| Project DEA | DIME Sample ID | Sample Taken Date | Link |
|---|---|---|---|
| No results found. | |||
Project Summary Graphs
Samples Taken and Tests performed per Month
Number of Samples
Sample Types
Number of Tests
Test Types
Material Types
Test Methods