Project Details

This page displays current information for project DEA: 07285404.

Project Information

Project IdentifiersProject ID: 7668
DEA: 07285404
EFIS: 0700020130
COOP: 074887
Permit Numbers: 0712NMC1791
DIST-CO-RTE-PM07-LA-187-07.5 /08.1
Award DateNot set
Closeout Date08/19/2021
Work DescriptionLight Rail Transit; Constructing 2 parallel pre-stressed box girder bridges. The bridge will be supported by 2 columns in the median of Venice Blvd on 95 feet long 12 feet diameter CIDH piles. Existing median will be demolished and relocated. 11 Drainage structures and 150 f
Location DescriptionIN LA CNTY IN LA FR .1M S/O CULVER BLVD TO .2M N/O NTL BLVD LIGHT RAIL TRANSIT
QA Service Level1 (Verified on 09/20/2012)

Caltrans Project Personnel

Personnel stored in Caltrans' project databases.

Email AddressFull NameRolePersonnel Source
PSvacina@exporail.netSvacina PaulOversight Resident EngineerCaltrans REO DB
frank_lotfi@dot.ca.govFrank LotfiStructural RepresentativeCaltrans SR DB

Samples

Samples submitted for this project.

Job Mix Formula (JMF)

JMFs associated with this project.

JMF IDStatusSubmitted ByCreated ByDate CreatedLink
No results found.

Precast Concrete Forms

Project DEADIME Sample IDSample Taken DateLink
No results found.

Project Summary Graphs


Samples Taken and Tests performed per Month


Number of Samples

Sample Types

Number of Tests

Test Types

Material Types

Test Methods