Project Details
This page displays current information for project DEA: 043A7734.
Project Information
| Project Identifiers | Project ID: 6858 DEA: 043A7734 Permit Numbers: 0412NRT0901 0412NRT0913 0411NDP1529 0410NMC0139 |
|---|---|
| DIST-CO-RTE-PM | 04-CC--0/5 |
| Award Date | 05/01/2010 |
| Closeout Date | 08/16/2013 |
| Work Description | The purpose of the I-80 Integrated Corridor Mobility (ICM) Traffic Signal Light Synchronization project (TLSP) is to assist in monitoring, and managing the traffic flow along the I-80 and State Route 123 corridor. |
| Location Description | I-80 AND SR 123, Var |
| QA Service Level | 1 (Verified on 12/21/2012) |
Caltrans Project Personnel
Personnel stored in Caltrans' project databases.
| Email Address | Full Name | Role | Personnel Source |
|---|---|---|---|
| nicholas.chreng@dot.ca.gov | Nicholas Chreng | Resident Engineer | Caltrans RE DB |
| mauricio_rivera@scengineers.com | Mauricio Rivera | Oversight Resident Engineer | Caltrans REO DB |
Samples
Samples submitted for this project.
| DIME Sample ID | Sample Taken Date | Sample Received Date | Sample Type | Material Type | Link |
|---|---|---|---|---|---|
| No results found. | |||||
Job Mix Formula (JMF)
JMFs associated with this project.
| JMF ID | Status | Submitted By | Created By | Date Created | Link |
|---|---|---|---|---|---|
| No results found. | |||||
Precast Concrete Forms
| Project DEA | DIME Sample ID | Sample Taken Date | Link |
|---|---|---|---|
| No results found. | |||
Project Summary Graphs
Samples Taken and Tests performed per Month
Number of Samples
Sample Types
Number of Tests
Test Types
Material Types
Test Methods