Project Details
This page displays current information for project DEA: 031A9204.
Project Information
Project Identifiers | Project ID: 212535 DEA: 031A9204 EFIS: 0300020608 |
---|---|
DIST-CO-RTE-PM | 03-SUT-20-5-11.3 |
Award Date | 06/11/2019 |
Closeout Date | 12/01/2021 |
Work Description | SUTTER BYPASS WIDENING AND REHAB |
Location Description | NEAR YUBA CITY FROM SUTTER BYPASS TO 0.1 MILE WEST OF LYTLE ROAD. |
QA Service Level | 1 (Verified on 07/23/2018) |
Caltrans Project Personnel
Personnel stored in Caltrans' project databases.
Email Address | Full Name | Role | Personnel Source |
---|---|---|---|
anthony.granados@dot.ca.gov | Anthony Granados | Resident Engineer | Caltrans RE DB |
glen.lawson@dot.ca.gov | Glen Lawson | Structural Representative | Caltrans SR DB |
Samples
Samples submitted for this project.
Displaying 1-10 of 73 results.
DIME Sample ID | Sample Taken Date | Sample Received Date | Sample Type | Material Type | Link |
---|---|---|---|---|---|
2020-06-04-42 | 06/04/2020 | 06/05/2020 | Verification | Hot Mix Asphalt | View |
2020-06-04-41 | 06/04/2020 | 06/05/2020 | Verification | Aggregate | View |
2020-09-21-40 | 09/21/2020 | 09/30/2020 | Department Acceptance | Asphalt Binder | View |
2020-09-21-39 | 09/21/2020 | 09/30/2020 | Department Acceptance | Asphalt Rubber Binder | View |
2020-09-14-30 | 09/14/2020 | 09/23/2020 | Department Acceptance | Asphalt Binder | View |
2020-09-11-14 | 09/11/2020 | 09/16/2020 | Department Acceptance | Asphalt Rubber Binder | View |
2020-08-31-7 | 08/31/2020 | 09/02/2020 | Quality Assurance | Concrete | View |
2020-09-01-11 | 09/01/2020 | 09/02/2020 | Quality Assurance | Concrete | View |
2020-08-29-6 | 08/29/2020 | 09/01/2020 | Department Acceptance | Asphalt Rubber Binder | View |
2020-08-26-14 | 08/26/2020 | 09/01/2020 | Department Acceptance | Asphalt Rubber Binder | View |
Job Mix Formula (JMF)
JMFs associated with this project.
Displaying 1-1 of 1 result.
JMF ID | Status | Submitted By | Created By | Date Created | Link |
---|---|---|---|---|---|
JMF3511-23-2021-38 | Submittal Accepted for Verification | CT D03 - Olivehurst Northern Regional Laboratory | 02/18/2021 | View |
Environmental Product Declaration (EPD)
EPDs material quantities submitted for this project.
Declaration Number | Material Type | Vendor | Submitted by | Quantity |
---|---|---|---|---|
No results found. |