Project Details

This page displays current information for project DEA: 081G1004.

Project Information

Project IdentifiersProject ID: 211091
DEA: 081G1004
EFIS: 0815000125
DIST-CO-RTE-PM08-RIV-74-36.5/42.6
Award Date02/25/2016
Closeout Date10/26/2016
Work DescriptionREPLACE ASPHALT CONCRETE SURFACING AND SLURRY SEAL
Location DescriptionREPLACE ASPHALT CONCRETE SURFACING AND SLURRY SEAL
QA Service Level1 (Verified on 05/03/2016)

Caltrans Project Personnel

Personnel stored in Caltrans' project databases.

Email AddressFull NameRolePersonnel Source
chat.yang@dot.ca.govChad YangResident EngineerCaltrans RE DB
prakash.gowda@dot.ca.govPrakash GowdaDistrict Materials Engineer - Field Lab FontanaCaltrans District Materials Engineer
zihui.li@dot.ca.govZihui LiDistrict Materials Engineer - SRL PCC/Agg/Soils LabCaltrans District Materials Engineer
cristina.paredes@dot.ca.govCristina ParedesDistrict Materials Engineer - SRL HMA and Binder LabsCaltrans District Materials Engineer
sittampalam.sathiskumar@dot.ca.govSittampalam SathiskumarDistrict Materials Engineer - DesignCaltrans District Materials Engineer
kaushalkumar.talati@dot.ca.govKaushalkumar TalatiDistrict Materials Engineer - Field Lab Barstow and HesperiaCaltrans District Materials Engineer
brian.teh@dot.ca.govBrian TehDistrict Materials Engineer - SRL STS and Field Lab BlytheCaltrans District Materials Engineer

Samples

Samples submitted for this project.

Displaying 1-10 of 12 results.
DIME Sample IDSample Taken DateSample Received DateSample TypeMaterial TypeLink
   
2016-06-23-606/23/201606/29/2016Department AcceptanceAggregateView
2016-06-22-1206/22/201606/29/2016Department AcceptanceAggregateView
2016-06-15-2406/15/201606/17/2016Department AcceptanceAggregateView
2016-06-14-806/14/201606/17/2016Department AcceptanceAggregateView
2016-06-13-1006/13/201606/17/2016Department AcceptanceAggregateView
2016-06-10-2006/10/201606/17/2016Department AcceptanceAggregateView
2016-06-09-806/09/201606/09/2016Department AcceptanceAggregateView
2016-06-08-1506/08/201606/09/2016Department AcceptanceAggregateView
2016-06-21-1406/21/201606/22/2016Department AcceptanceAggregateView
2016-06-20-606/20/201606/22/2016Department AcceptanceAggregateView

Job Mix Formula (JMF)

JMFs associated with this project.

JMF IDStatusSubmitted ByCreated ByDate CreatedLink
No results found.

Precast Concrete Forms

Project DEADIME Sample IDSample Taken DateLink
No results found.

Project Summary Graphs


Samples Taken and Tests performed per Month


Number of Samples

Sample Types

Number of Tests

Test Types

Material Types

Test Methods