Project Details
This page displays current information for project DEA: 060W79U4.
Project Information
| Project Identifiers | Project ID: 1000510 DEA: 060W79U4 EFIS: 0622000189 |
|---|---|
| DIST-CO-RTE-PM | 06-KER,TUL-99-56.4/57.6,0.0/13.5 |
| Award Date | 04/10/2025 |
| Closeout Date | Not set |
| Work Description | RDWY EXC, HMA, AGGREGATE BASE, CRCP, SIGN STR, AND STR EXC. |
| Location Description | KERN AND TULARE COUNTIES IN AND NEAR DELANO FROM 0.2 MILE SOUTH OF CECIL AVENUE OVERCROSSING TO 0.7 MILE NORTH OF AVENUE 100 OVERCROSSING |
| QA Service Level | 1 (Verified on 08/26/2024) |
Caltrans Project Personnel
Personnel stored in Caltrans' project databases.
| Email Address | Full Name | Role | Personnel Source |
|---|---|---|---|
| jake.garcia@dot.ca.gov | Jake Garcia | Resident Engineer | Caltrans RE DB |
| justin.palmaymesa@dot.ca.gov | Justin Palmaymesa | METS REP | Caltrans METS REP DB |
Samples
Samples submitted for this project.
Displaying 1-10 of 437 results.
| DIME Sample ID | Sample Taken Date | Sample Received Date | Sample Type | Material Type | Link |
|---|---|---|---|---|---|
| 2026-01-12-7 | 01/12/2026 | 01/12/2026 | Acceptance | Aggregate | View |
| 2026-01-02-1 | 01/02/2026 | 01/02/2026 | Quality Control | Aggregate | View |
| 2025-12-03-70 | 12/03/2025 | 12/03/2025 | Quality Control | Aggregate | View |
| 2025-12-03-69 | 12/03/2025 | 12/04/2025 | Quality Control | Concrete | View |
| 2025-12-23-8 | 12/23/2025 | 12/25/2025 | Quality Control | Concrete | View |
| 2025-12-23-7 | 12/23/2025 | 12/23/2025 | Quality Control | Aggregate | View |
| 2025-12-22-17 | 12/22/2025 | 12/22/2025 | Quality Control | Aggregate | View |
| 2025-12-22-16 | 12/22/2025 | 12/23/2025 | Quality Control | Concrete | View |
| 2025-12-23-3 | 12/23/2025 | 12/23/2025 | Acceptance | Aggregate | View |
| 2025-12-19-9 | 12/19/2025 | 12/19/2025 | Quality Control | Aggregate | View |
Job Mix Formula (JMF)
JMFs associated with this project.
| JMF ID | Status | Submitted By | Created By | Date Created | Link |
|---|---|---|---|---|---|
| No results found. | |||||
Project Summary Graphs
Samples Taken and Tests performed per Month
Number of Samples
Sample Types
Number of Tests
Test Types
Material Types
Test Methods
