Project Details
This page displays current information for project DEA: 060W79U4.
Project Information
| Project Identifiers | Project ID: 1000510 DEA: 060W79U4 EFIS: 0622000189 |
|---|---|
| DIST-CO-RTE-PM | 06-KER,TUL-99-56.4/57.6,0.0/13.5 |
| Award Date | 04/10/2025 |
| Closeout Date | Not set |
| Work Description | RDWY EXC, HMA, AGGREGATE BASE, CRCP, SIGN STR, AND STR EXC. |
| Location Description | KERN AND TULARE COUNTIES IN AND NEAR DELANO FROM 0.2 MILE SOUTH OF CECIL AVENUE OVERCROSSING TO 0.7 MILE NORTH OF AVENUE 100 OVERCROSSING |
| QA Service Level | 1 (Verified on 08/26/2024) |
Caltrans Project Personnel
Personnel stored in Caltrans' project databases.
| Email Address | Full Name | Role | Personnel Source |
|---|---|---|---|
| jake.garcia@dot.ca.gov | Jake Garcia | Resident Engineer | Caltrans RE DB |
| justin.palmaymesa@dot.ca.gov | Justin Palmaymesa | METS REP | Caltrans METS REP DB |
Samples
Samples submitted for this project.
Displaying 51-60 of 389 results.
| DIME Sample ID | Sample Taken Date | Sample Received Date | Sample Type | Material Type | Link |
|---|---|---|---|---|---|
| 2025-10-03-67 | 10/03/2025 | 10/03/2025 | Quality Control | Concrete | View |
| 2025-10-02-54 | 10/02/2025 | 10/03/2025 | Quality Control | Aggregate | View |
| 2025-10-02-53 | 10/02/2025 | 10/03/2025 | Quality Control | Concrete | View |
| 2025-11-12-35 | 11/12/2025 | 11/17/2025 | Quality Assurance | Asphaltic Emulsion | View |
| 2025-11-13-32 | 11/13/2025 | 11/17/2025 | Quality Assurance | Concrete | View |
| 2025-11-13-22 | 11/13/2025 | 11/14/2025 | Acceptance | Aggregate | View |
| 2025-11-13-21 | 11/13/2025 | 11/14/2025 | Acceptance | Hot Mix Asphalt | View |
| 2025-11-13-2 | 11/13/2025 | 11/13/2025 | Acceptance | Aggregate | View |
| 2025-11-06-35 | 11/06/2025 | 11/12/2025 | Quality Assurance | Asphalt Binder | View |
| 2025-11-05-44 | 11/05/2025 | 11/12/2025 | Quality Assurance | Asphalt Binder | View |
Job Mix Formula (JMF)
JMFs associated with this project.
| JMF ID | Status | Submitted By | Created By | Date Created | Link |
|---|---|---|---|---|---|
| No results found. | |||||
Precast Concrete Forms
| Project DEA | DIME Sample ID | Sample Taken Date | Link |
|---|---|---|---|
| No results found. | |||
Project Summary Graphs
Samples Taken and Tests performed per Month
Number of Samples
Sample Types
Number of Tests
Test Types
Material Types
Test Methods
