Project Details
This page displays current information for project DEA: 024H0104.
Project Information
| Project Identifiers | Project ID: 215734 DEA: 024H0104 EFIS: 0218000068 |
|---|---|
| DIST-CO-RTE-PM | 02-PLU-70-78.3/90.3 |
| Award Date | 01/29/2025 |
| Closeout Date | Not set |
| Work Description | REPLACE AC SURFACING, PLACE HMA AND THERMOPLASTIC TRAFFIC STRIPING. |
| Location Description | PLUMAS COUNTY NEAR PORTOLA FROM 0.4 MILE WEST OF BIG GRIZZLY CREEK BRIDGE TO 0.8 MILE WEST OF SUMMIT SCHOOL DRIVE |
| QA Service Level | 1 (Verified on 07/08/2021) |
Caltrans Project Personnel
Personnel stored in Caltrans' project databases.
| Email Address | Full Name | Role | Personnel Source |
|---|---|---|---|
| mike.zdenek@dot.ca.gov | Mike Zdenek | Resident Engineer | Caltrans RE DB |
| peter.gan@dot.ca.gov | Peter Gan | METS REP | Caltrans METS REP DB |
Samples
Samples submitted for this project.
Displaying 21-30 of 35 results.
| DIME Sample ID | Sample Taken Date | Sample Received Date | Sample Type | Material Type | Link |
|---|---|---|---|---|---|
| 2022-01-20-53 | 01/20/2022 | 01/21/2022 | Preliminary | Soil | View |
| 2022-01-20-52 | 01/20/2022 | 01/21/2022 | Preliminary | Soil | View |
| 2022-01-20-51 | 01/20/2022 | 01/21/2022 | Preliminary | Soil | View |
| 2022-01-20-46 | 01/20/2022 | 01/21/2022 | Preliminary | Soil | View |
| 2021-04-08-40 | 04/08/2021 | 04/09/2021 | Preliminary | Soil | View |
| 2021-04-08-39 | 04/08/2021 | 04/09/2021 | Preliminary | Soil | View |
| 2021-04-08-38 | 04/08/2021 | 04/09/2021 | Preliminary | Soil | View |
| 2021-04-08-37 | 04/08/2021 | 04/09/2021 | Preliminary | Soil | View |
| 2021-04-08-36 | 04/08/2021 | 04/09/2021 | Preliminary | Soil | View |
| 2021-04-08-35 | 04/08/2021 | 04/09/2021 | Preliminary | Soil | View |
Job Mix Formula (JMF)
JMFs associated with this project.
| JMF ID | Status | Submitted By | Created By | Date Created | Link |
|---|---|---|---|---|---|
| No results found. | |||||
Precast Concrete Forms
| Project DEA | DIME Sample ID | Sample Taken Date | Link |
|---|---|---|---|
| No results found. | |||
Project Summary Graphs
Samples Taken and Tests performed per Month
Number of Samples
Sample Types
Number of Tests
Test Types
Material Types
Test Methods