Project IDProject IdentifiersDIST-CO-RTE-PMWork DescriptionLocation DescriptionCaltrans Closeout DateMETS Service LevelActions
     
213988Project ID: 213988
DEA: 081E7104
EFIS: 0814000079
08--10-31.62/31.92I-10 University Street Improvement ProjectPost Mile 31.62/31.92 on Interstate 10 in teh City if Redlands,Ca 2 (03/08/2019)Details CEM-3701 Report
214038Project ID: 214038
DEA: 07315404
EFIS: 0715000185
Permit Numbers: 0718AOP2643 0719ART0238 0719ART1716
07---3.4/3.8Roadway widening of northbound (NB) State Route 213 from 200' south of Avenida Aprenda to 500' north of Green Hills Drive (PM 3.4/3.8). Widening will accommodate the addition of one NB through lane and shoulder, two new bus turnouts, two new driveway approaches to the new development, and moWestern Avenue (SR-213), Los Angeles/Rancho Palos Verdes06/17/20212 (03/28/2019)Details CEM-3701 Report
214019Project ID: 214019
DEA: 07309203
EFIS: 0714000267
Permit Numbers: 0716AMC1295 0718ART2606
07-LA-605-23.3I-605 Ramp Widening & Live Oak Avenue IntersectionThe reconstruction of the I-605 Northbound off-ramp at Live Oak Avenue will improve both directions of acce ss to Live Oak Avenue. The direct ramp to eastbound Live Oak Avenue will be widened to provide dual right lanes at Live Oak Avenue,06/17/20212 (03/05/2019)Details CEM-3701 Report
214101Project ID: 214101
Permit Numbers: 0417NMC1910
04-SM-82-9.35-10.07The Peninsula Corridor Joint Powers Board (JPB), which operates the San Francisco Bay Area's Caltrain passenger rail intends to extend 28th Avenue and 31st Avenue west of El Camino Real (SR 82) in the same location as existing driveway access points... 08/13/20212 (08/28/2019)Details CEM-3701 Report
214131Project ID: 214131
DEA: 080N69U4
EFIS: 0812000307
COOP: 081635
08-RIV-60-22.1/22.6Improving Operation efficiency and traffic flow in the SR-60 Truck Corridor in Moreno Valley. Widening inside and outside shoulders in 6 stages.R-60 Truck Climbing Lane . Construction of new east and west bound truck lanes from Gilman Springs road to 1.37 miles west if Jack Rabbit trail. Existing shoulders will be widened to standard 10 ft inside and 12 ft outside respectively. 2 (04/30/2019)Details CEM-3701 Report
214168Project ID: 214168
DEA: 042358A4
EFIS: 0419000385
04-SM-101-16.3/17.1Interchange Landscaping Improvemetns  2 (08/28/2019)Details CEM-3701 Report
214248Project ID: 214248
DEA: 041K2803
EFIS: 0416000224
COOP: 042753
04-SCL-101-28.4.28.9Modification of US 101/Blossom Hill Road Interchange 05/26/20222 (07/09/2019)Details CEM-3701 Report
214197Project ID: 214197
DEA: 100H8904
EFIS: 1012000159
10-SJ-120-R0.9/R3.3State Route 120/McKinley Avenue Interchange Project in cooperation with City of Manteca and San Joaquin Council of Governments.  2 (06/26/2019)Details CEM-3701 Report
214199Project ID: 214199
DEA: 024F4204
EFIS: 0212000111
COOP: 020155
Permit Numbers: 0219NRP0130
02-LAS-36-26.79Construct a new public road connection and signal on SR 36. Project includes on intersection of signal and light poles.SR-36 at connection of new Skyline Road extension (PM 26.79) in Susanville, Lassen County.04/15/20202 (06/03/2019)Details CEM-3701 Report
214458Project ID: 214458
DEA: 07316304
EFIS: 0715000199
Permit Numbers: 0719AOP1456
07---3.274/-1Roadway Widening (includes new pavement section, new curb & gutter, and sidewalk modifications) removal of raised medians, curb ramp construction, signing, striping, traffic signal modifications/installations.The proposed improvements will be implemented at the following intersections:*IntersecWestern Avenue (SR-213) and various locations, Los Angeles, Rancho Palos Verdes, Lomita11/30/00-12 (01/22/2020)Details CEM-3701 Report