Project IDProject IdentifiersDIST-CO-RTE-PMWork DescriptionLocation DescriptionCaltrans Closeout DateMETS Service LevelActions
     
212632Project ID: 212632
DEA: 031H2604
EFIS: 0316000079
03-NEV-80-19.3CONSTRUCT NEW WATER SUPPLY.NEVADA COUNTY IN TRUCKEE AT THE DONNER PASS COMMERCIAL VEHICLE ENFORCEMENT FACILITY12/26/20181 (09/15/2017)Details CEM-3701 Report
215064Project ID: 215064
DEA: 032H3004
EFIS: 0317000092
03-NEV-80-19.3REPLACE LIGHT FIXTURES, OVERHEAD DOORS AND INSPECTION DESK STATIONS.NEVADA COUNTY IN TRUCKEE AT THE DONNER PASS COMMERCIAL VEHICLE ENFORCEMENT FACILITY05/04/20211 (07/20/2020)Details CEM-3701 Report
215683Project ID: 215683
DEA: 032H30A4
EFIS: 0317000092
03-NEV-80-19.3REPLACE LIGHT FIXTURES, OVERHEAD DOORS AND INSPECTION DESK STATIONS.NEVADA COUNTY IN TRUCKEE AT THE DONNER PASS COMMERCIAL VEHICLE ENFORCEMENT FACILITY05/25/20221 (05/20/2021)Details CEM-3701 Report
212867Project ID: 212867
DEA: 033F9204
EFIS: 0313000239
03-NEV-80-19.1,27.4REPLACE SAND AND SALT HOUSES.NEVADA COUNTY IN TRUCKEE AT THE DONNER PASS INSPECTION FACILITY AND AT FLORISTON AT THE FLORISTON SAND AND SALT HOUSES05/05/20201 (12/18/2017)Details CEM-3701 Report
994727Project ID: 994727
DEA: 031J2604
EFIS: 0320000184
03-NEV-80-16.3/18.8GRIND CONCRETE, PLACE POLYESTER CONCRETE INLAY, AND RESTRIPE.NEVADA COUNTY IN TRUCKEE FROM 0.3 MILE WEST OF 80/267/89N SEPARATION TO 0.5 MILE EAST OF POLARIS UNDERCROSSING06/23/20251 (05/15/2023)Details CEM-3701 Report
214763Project ID: 214763
DEA: 031J0304
EFIS: 0320000065
03-NEV-80-R12.2/13.3GRIND EXIST CONC PVMT, HMA, CONST MED BARRIER, & COLD PLANE AC PVMT.NEVADA COUNTY IN TRUCKEE FROM 1.0 MILE WEST OF DONNER PASS ROAD OVERCROSSING TO 0.1 MILE EAST OF DONNER PASS ROAD OVERCROSSING03/16/20211 (03/24/2020)Details CEM-3701 Report
213214Project ID: 213214
DEA: 030G8304
EFIS: 0316000265
03-NEV-174-0.1/0.9REPLACE CULVERTS.NEVADA COUNTY NEAR CHICAGO PARK AT VARIOUS LOCATIONS FROM 0.1 MILE EAST OF PLACER COUNTY LINE TO 0.1 MILE WEST OF MOUNT OLIVE ROAD01/09/20191 (08/01/2018)Details CEM-3701 Report
994564Project ID: 994564
DEA: 033J1904
EFIS: 0322000218
03-NEV-80-R59.6/R59.9PLACE THRIE BEAM BARRIER AND CONCRETE BARRIER.NEVADA COUNTY NEAR CISCO GROVE FROM 0.1 MILE EAST OF ROUTE 20 TO 2.3 MILES WEST OF EAGLE LAKES ROAD04/11/20251 (05/15/2023)Details CEM-3701 Report
209720Project ID: 209720
DEA: 033E1104
EFIS: 0300020256
03-NEV-80-28.0PAINT STRUCTURESNEVADA COUNTY NEAR FLORISTON AT TRUCKEE RIVER BRIDGE10/28/20151 (12/26/2014)Details CEM-3701 Report
994835Project ID: 994835
DEA: 032J9104
EFIS: 0322000136
03-NEV-80-25.5/27.3POLYESTER CONC, REPLACE JOINT SEAL (ASPHALT RUBBER), CONCRETE BARRIER.NEVADA COUNTY NEAR FLORISTON FROM 1.9 MILES EAST OF HINTON ROAD TO TRUCKEE RIVER BRIDGE06/02/20251 (05/22/2023)Details CEM-3701 Report