Projects

To search for a project, enter filter criteria in the appropriate input field below. If a project is not listed, please contact a METS Representative for assistance.
Displaying 10251-10260 of 19149 results.
Project IDProject IdentifiersDIST-CO-RTE-PMWork DescriptionLocation DescriptionCaltrans Closeout DateMETS Service LevelActions
     
4759Project ID: 4759
EFIS: 0000001155
Permit Numbers: 0808NMC0532 08096DP0134
08-SBD-15-3/5.3Enter onto Interstate 15 (I-15) right-of-way at Foothill Blvd southbound on-ramp in the City of Rancho Cucamonga to improve the on-ramp as per plans date stamped November 12, 2008 by California Department of Transportation Encroachment Permits Office and/Foothill Boulevard, Rancho Cucamonga03/01/2010NOT VERIFIEDDetails CEM-3701 Report
214547Project ID: 214547
EFIS: 000020505N
Permit Numbers: 0719NMC2148
07---3.22/-1Traffic signal modification. New poles, detector loops, conduit and conductors.Foothill Boulevard, Claremont06/17/20211 (01/08/2020)Details CEM-3701 Report
213071Project ID: 213071
Permit Numbers: 0716NMC1797 07186DP0399 0718NRT0414
07-LA-66-2.5/2.5Traffic signal modification, ADA ramps, OverlayFoothill Blvd, Pomona06/17/20211 (01/25/2018)Details CEM-3701 Report
993579Project ID: 993579
Permit Numbers: 07216SN3965
07---2.538Modify traffic signal for the conversion of the northbound Garey Avenue curb lane to a right-turn only lane at the intersection of Route 66 (Foothill Boulevard) and Garey Avenue in the City of Pomona. Perform associated traffic control. All work in accordance with the current State specifications aFoothil Blvd, Pomona 1 (02/15/2022)Details CEM-3701 Report
993883Project ID: 993883
DEA: 081M1504
08-SBD--Building WorkFontana, CA 1 (06/10/2022)Details CEM-3701 Report
209885Project ID: 209885
Permit Numbers: 08136MC0203
08-RIV-74-45.106/45.18Enter onto State Highway 74 right-of-way (Florida Avenue) between Fairview Avenue and 4th Street to install the following: New pavement, grind and overlay pavement, curb & gutter, ADA ramps, meandering sidewalk, landscape, 12" service waterline, conduits and pull boxes necessary for SCE toFlorida Avenue, Valle Vista07/31/20181 (09/04/2014)Details CEM-3701 Report
213909Project ID: 213909
Permit Numbers: 0618NTN0211 06196DP0068 0618NRT0988 0619NRT0152
06-FRE-145-23.67Install 4-72" Rubber Gasket Reinforced Concrete Pipe (RGRCP) crossing under State Route 145 using Bore and Jack method (as shown on the attached plans). The bore and receiving pits are located outside the State Right of Way.Floral Av, Helm11/30/00-11 (03/12/2019)Details CEM-3701 Report
210323Project ID: 210323
Permit Numbers: 0514NSN0619 0515NRT0656 0516NRT0168
05-SLO-101-15.9/15.91. Remove existing mast-arm signal poles on the NW and SE corners of the project intersection and install new longer mast-arm signal poles.2. Replace existing signal cable with new signal cables to accommodate wiring for new left turn phasing.3. Reprogram signal controller to add protected left turFive Cities Dr./Hwy 101 SB Ramps, Pismo Beach08/16/20191 (07/25/2016)Details CEM-3701 Report
209172Project ID: 209172
DEA: 041E40C4
EFIS: 0400000544
04-NAP-29-New contract for 04-1E4004, 04-1E40A4 - Same contract docs. - Reconstruction keeper plates. Clean and paint.First Street Overcrossing in Napa10/21/20141 (10/31/2013)Details CEM-3701 Report
7298Project ID: 7298
EFIS: 0000001155
Permit Numbers: 1213NRT0005 1212NRW0679 1213NRW0117 1213NRW0679 1209NMC0140 12126DP0586
12-ORA-5-44.26/44.26Perform the work authorized under Caltrans Encroachment Permit No. 1209-NMC- 0140 issued to the City of Buena Park in accordance with all the terms and conditions of that original permit. Permittee shall keep complete copies of both permits on the job sitFirestone Boulevard, Buena Park07/31/20181 (01/14/2013)Details CEM-3701 Report