Summary for Test 2020-04-29-8-1

Test performed: AASHTO T30-19

Project Information

Project IdentifiersProject ID: 99999
DEA: 0322222
DIST-CO-RTE-PM03-SAC,OMG-888,99,80-0.6-0.6
Award DateNot set
Closeout DateNot set
Work DescriptionTHIS PROJECT RECORD WAS ADDED FOR DIME TESTERS - DATA SUBMITTED FOR THIS PROJECT SHOULD NOT BE USED FOR ANY OTHER PURPOSES.
Location DescriptionTHIS PROJECT RECORD WAS ADDED FOR DIME TESTERS - DATA SUBMITTED FOR THIS PROJECT SHOULD NOT BE USED FOR ANY OTHER PURPOSES.
QA Service Level (Verified on 04/05/2013)

Sample Information

Sample Taken Date04/29/2020 Sample Unique Key8
Will the laboratory/organization for which you are a member perform testing on this material sample?Yes Date that the sample was received by the laboratory/organization performing the testing04/29/2020
Sample typeVerification A brief description of the sampleRAp for Type A JMF
The quantity of what the sample constitutesbag of RAP From where was the sample collectedSource
First name of sampler or witnessed byClinton Last name of sampler or witnessed byEdmiston
Title of sampler Telephone number of sampler
Laboratory sample identification Linked DIME Sample ID
The fabricator/manufacturer/facility nameGeorge Reed Plant Transportation Laboratory (TL) Number
Inspector Lot Number from the Transportation Laboratory (TL) Form Structure unique identifier
Structure name

Material Information

Material TypeReclaimed Asphalt Pavement RAP SourcePlant
Aggregate SizeUnknown Aggregate SourceUnknown
RAP Stockpile Stockpile Size (tons)Unknown
Reclaimed Asphalt Pavement Mix NumberNot set

Test Details

DIME Sample ID: 2020-04-29-8
DIME Test ID: 2020-04-29-8-1
Testing Lab: CT HQ - Sacramento Hot Mix Asphalt Laboratory
Test Method: AASHTO T30-19: Standard Method of Test for Mechanical Analysis of Extracted Aggregate (Mechanical Analysis)
Test Release Date: 2020-04-29

Test Results


Does this test use 1/4 sieve?: Yes
Is an aggregate correction factor used?: No
Input Type: Calculated
Tester's full name: John Doe
Date of test: 04/29/2020
Cumulative percent passing the 2 in. sieve: 100 %
Cumulative percent passing the 1 1/2 in. sieve: 100 %
Cumulative percent passing the 1 in. sieve: 100 %
Cumulative percent passing the 3/4 in. sieve: 100 %
Cumulative percent passing the 1/2 in. sieve: 100 %
Cumulative percent passing the 3/8 in. sieve: 99.2 %
Cumulative percent passing the 1/4 in. sieve: 99.2 %
Cumulative percent passing the #4 sieve: 73.1 %
Cumulative percent passing the #8 sieve: 53 %
Cumulative percent passing the #16 sieve: 38.9 %
Cumulative percent passing the #30 sieve: 27.6 %
Cumulative percent passing the #50 sieve: 18.3 %
Cumulative percent passing the #100 sieve: 12.2 %
Cumulative percent passing the #200 sieve: 8.5 %
General comments (publicly viewable) (Max 1000 characters):

Test was verified on 4/29/2020