Test 2020-02-04-19-1 (CTM 202-November 2011) Summary

Project Information
Project IdentifiersProject ID: 66666
DEA: APP
EFIS: 0019000052
DIST-CO-RTE-PM59---
Work DescriptionSpecial project for submitting Sample information for Aggregate Pre-approval Program (APP). Object Code: 1025. J2 DEA: 912680.
Location DescriptionNot set
Sample Information
Sample Taken Date2/4/2020 Sample Unique Key19
Will the laboratory/organization for which you are a member perform testing on this material sample?Yes Date that the sample was received by the laboratory/organization performing the testing1/27/2020
Sample typeAggregate Prequalification Program A brief description of the sampleWashed Concrete Sand
The quantity of what the sample constitutes4 BAGS From where was the sample collectedSource
First name of sampler or witnessed byManolito Last name of sampler or witnessed byLimos
Title of samplerQUALITY CONTROL Laboratory sample identification9294
The fabricator/manufacturer/facility nameVulcan Sun Valley - Big Rock Creek Transportation Laboratory (TL) NumberC2019-12-06-15 DIME
Inspector Lot Number from the Transportation Laboratory (TL) Form Structure unique identifier
Structure name
Material Information
Material TypeAggregate Source Identification (SMARA or name of Pit)91-19-0021::BIG ROCK CREEK
The fabricator's/manufacturer's product name for the sampleUnknown The fabricator/manufacturer designation for the sampleUnknown
The plant numberUnknown A detailed description of where the material sample was collectedStockpile @ Plant
Where the material sample would have been placed if not sampledUnknown Primary Aggregate Nominal Sizefine
The concrete mix design numberUnknown Lot numberUnknown
Sublot numberUnknown HMA Design ID
Test Details
DIME Sample ID: 2020-02-04-19
DIME Test ID: 2020-02-04-19-1
Testing Lab: CT - Southern Regional Laboratory
Test Method: CTM 202-November 2011: Method of Test for Sieve Analysis of Fine and Coarse Aggregates
Test Release Date: 2020-03-16
Test Results

What size aggregate is being tested?: Fine Aggregate
Individual or cumulative mass retained on each sieve?: Cumulative Mass Retained
Input Type: Calculated
Tester's full name: EDMOUND JABBOUR
Date of test: 02/07/2020
Cumulative percent passing the 3/8 in. sieve:100 %
Cumulative percent passing the #4 sieve:98 %
Cumulative percent passing the #8 sieve:76 %
Cumulative percent passing the #16 sieve:57 %
Cumulative percent passing the #30 sieve:37 %
Cumulative percent passing the #50 sieve:19 %
Cumulative percent passing the #100 sieve:5 %
Cumulative percent passing the #200 sieve:2 %
General comments (publicly viewable) (Max 1000 characters):

Test was verified on 03/16/2020