Print Report | Back to Test Summary

Testing Report for 2021-04-01-34-3

Note: Fields with no data or with a value of "Unknown" will not be displayed on the print out.

Project Information

DEA: 030F2904
EFIS: 0314000101
Project ID: 215062
QA Service Level: 1
DIST-CO-RTE-PM: 03-BUT-99-14.9/15.7
Work Description: CONSTRUCT BRIDGE AND ROADWAY; & REMOVE BRIDGE.
Location Description: BUTTE COUNTY ABOUT 10 MILES NORTH OF GRIDLEY FROM 0.3 MILE SOUTH TO 0.5 MILE NORTH OF NELSON AVENUE
Contractor Name: Unknown
Contractor Address: Unknown
Resident Engineer: Daniel Rechs
Structure Rep.: James Ralston

Sample Information

DIME Sample ID: 2021-04-01-34
TL Number from the TL Form: C706327
Sample Submitted By Organization: CT D03 - North Region Materials Lab
Sample Organization Contact: (530) 741-4238
Type of Sample: Verification
Type of Material: Reclaimed Asphalt Pavement
Sample Taken Date: 4/1/2021
Date that the sample was received by the laboratory/organization performing the testing: 4/1/2021
The quantity of what the sample constitutes: JMF Verification
A brief description of the sample: RAP
From where was the sample collected: Manufacturer
Laboratory sample identification:
Structure unique identifier:
Structure name:
The fabricator/manufacturer/facility name: Teichert - Hallwood Plant

Material Information

RAP Source: Teichert Hallwood RAP Bin 1
Aggregate Size:
Aggregate Source:
RAP Stockpile: Static
Stockpile Size (tons): Unknown

Test Information

DIME Test ID: 2021-04-01-34-3
Test Method: AASHTO T30-19: Standard Method of Test for Mechanical Analysis of Extracted Aggregate (Mechanical Analysis)
Date Tested: 4/28/2021
Verified Date: 6/3/2021
Submitted By Organization: CT D03 - North Region Materials Lab
Organization Address: 5330 Arboga Rd,
Organization City: Olivehurst
Organization State: CA
Organization Zipcode: 95961
Organization Email: jeff.herbert@dot.ca.gov
Organization Phone: (530) 741-4238
General Comments for this Test: JMF21-020B.
Test Result Compliance: complies
Additional Comments When Verified : JMF21-020B

Submitted Test Results

Does this test use 1/4 sieve?: No
Cumulative percent passing the 2 in. sieve: 100 %
Cumulative percent passing the 1 1/2 in. sieve: 100 %
Cumulative percent passing the 1 in. sieve: 100 %
Cumulative percent passing the 3/4 in. sieve: 100 %
Cumulative percent passing the 1/2 in. sieve: 96 %
Cumulative percent passing the 3/8 in. sieve: 85 %
Cumulative percent passing the #4 sieve: 58 %
Cumulative percent passing the #8 sieve: 40 %
Cumulative percent passing the #16 sieve: 30 %
Cumulative percent passing the #30 sieve: 23 %
Cumulative percent passing the #50 sieve: 16 %
Cumulative percent passing the #100 sieve: 12 %
Cumulative percent passing the #200 sieve: 9 %