Sample Record

Owner Lab

  • MCM Construction, Inc.

DIME Sample ID 2023-10-24-111

Project Information

Project IdentifiersProject ID: 994245
DEA: 051H4304
EFIS: 0516000073
DIST-CO-RTE-PM05-SB-101-21.4/21.9
Award Date03/02/2023
Closeout DateNot set
Work DescriptionSan Jose Creek Bridge replacement
Location DescriptionSANTA BARBARA COUNTY IN GOLETA FROM ROUTE 101/217 SEPARATION TO 0.3 MILE NORTH OF SAN JOSE CREEK BRIDGE
QA Service Level1 (Verified on 09/19/2022)

Sample Information

Sample Taken Date10/24/2023 Sample Unique Key111
Will the laboratory/organization for which you are a member perform testing on this material sample?Yes Date that the sample was received by the laboratory/organization performing the testing10/25/2023
Sample typeQuality Control A brief description of the sampleCIDH concrete
The quantity of what the sample constitutes18 CY From where was the sample collectedJob Site
First name of sampler or witnessed byPeter Last name of sampler or witnessed byKim
Title of sampler Telephone number of sampler
Laboratory sample identification Linked DIME Sample ID
The fabricator/manufacturer/facility nameCEMEX Transportation Laboratory (TL) Number
Inspector Lot Number from the Transportation Laboratory (TL) Form Structure unique identifier
Structure nameSan Jose Creek Bridge (NB)

Material Information

Material TypeConcrete The concrete mix design number1610898
The truck number from where the sample was collected The batch plant ticket number from where the sample was collected30985838
Concrete batch plant The fabricator/manufacturer designation for the sample
A detailed description of where the material sample was collectedConcrete pump hopper Where the material sample would have been placed if not sampled
From Lot No. Bag Lot No.

Submitted Tests

DIME Test IDTest MethodTester Name, Testing LabDate TestedSubmitted ByVerified?Release DateTest CommentsActions
No results found.

Sample File Attachments

File NameExtensionDate UploadedActions
No results found.

Test File Attachments