Project Information

Project IdentifiersProject ID: 209695
DEA: 08347704
EFIS: 0800000616
DIST-CO-RTE-PM08-SBD-SR-58-0/12.9
Award Date11/10/2017
Closeout Date01/14/2021
Work Description(Alternative Delivery) The CMGC project will upgrade SR 58 from 2- to 4-lanes in San Bernardino County from the Kern County line to 7.5 miles east of US-395.
Location DescriptionSR-58 / 395 Kramer Junction project. In San Bernardino County from the Kern County line to 7.5 miles east of US-395.
QA Service Level1 (Verified on 12/01/2017)

Sample Information

Sample Taken Date10/26/2018 Sample Unique Key6
Will the laboratory/organization for which you are a member perform testing on this material sample?Yes Date that the sample was received by the laboratory/organization performing the testing10/29/2018
Sample typeQuality Assurance A brief description of the sample Dayton Superior coupler
The quantity of what the sample constitutes8 From where was the sample collectedJob Site
First name of sampler or witnessed byNagi Last name of sampler or witnessed byWaseal
Title of samplerUnknown Telephone number of samplerUnknown
Laboratory sample identificationUnknown Linked DIME Sample IDUnknown
The fabricator/manufacturer/facility nameDayton Superior CMC Rebar Transportation Laboratory (TL) NumberC705429 C705428
Inspector Lot Number from the Transportation Laboratory (TL) FormUnknown Structure unique identifierNot set
Structure nameNot set

Material Information

Material TypeSMTL TM5 - Couplers Production or Authorization TestingProduction Testing
Service or UltimateService Material Standard CodeASTM A706
Material Grade60 Rebar ManufacturerCMC Rebar
Coupler ManufacturerDayton Superior Intermediate Assembler or FabricatorUnknown
Rebar Size8 Coupler ModelDayton Bar lock couplers
Coating StandardsUncoated Shape of RebarStraight
Rebar Hoop DiameterUnknown Rebar Hoop FabricatorUnknown
Coupler Component Heat/Lot Number(s)162061 Rebar Heat Number(s)4070637
Rebar Size 2 Coupler Unique IDNot set

Submitted Tests

DIME Test IDTest MethodTester Name, Testing LabDate TestedSubmitted ByVerified?Release DateTest CommentsActions
2018-10-26-6-1CTM 670-December 2013: Method of Tests for Mechanical and Welded Reinforcing Steel Splices (Tensile Slip)Brian, CT HQ - Sacramento Structural Materials Testing Laboratory10/31/2018Brian
Yes
11/08/2018Service Splice
2018-10-26-6-2CTM 670-December 2013: Method of Tests for Mechanical and Welded Reinforcing Steel Splices (Tensile Slip)Brian, CT HQ - Sacramento Structural Materials Testing Laboratory10/31/2018Brian
Yes
11/08/2018Service Splice
2018-10-26-6-3CTM 670-December 2013: Method of Tests for Mechanical and Welded Reinforcing Steel Splices (Tensile Slip)Brian, CT HQ - Sacramento Structural Materials Testing Laboratory10/31/2018Brian
Yes
11/08/2018Service Splice
2018-10-26-6-4CTM 670-December 2013: Method of Tests for Mechanical and Welded Reinforcing Steel Splices (Tensile Slip)Brian, CT HQ - Sacramento Structural Materials Testing Laboratory10/31/2018Brian
Yes
11/08/2018Service Splice
2018-10-26-6-5CTM 670-December 2013: Method of Tests for Mechanical and Welded Reinforcing Steel Splices (Tensile Slip)Brian, CT HQ - Sacramento Structural Materials Testing Laboratory10/31/2018Brian
Yes
11/08/2018Service Splice
2018-10-26-6-6CTM 670-December 2013: Method of Tests for Mechanical and Welded Reinforcing Steel Splices (Tensile Slip)Brian, CT HQ - Sacramento Structural Materials Testing Laboratory10/31/2018Brian
Yes
11/08/2018Service Splice
2018-10-26-6-7CTM 670-December 2013: Method of Tests for Mechanical and Welded Reinforcing Steel Splices (Tensile Slip)Brian, CT HQ - Sacramento Structural Materials Testing Laboratory10/31/2018Brian
Yes
11/08/2018Service Splice

Sample File Attachments

File NameExtensionDate UploadedActions
No results found.

Test File Attachments


DIME Test ID: 2018-10-26-6-1 CTM 670-December 2013 (Verified)
DIME Test ID: 2018-10-26-6-2 CTM 670-December 2013 (Verified)
DIME Test ID: 2018-10-26-6-3 CTM 670-December 2013 (Verified)
DIME Test ID: 2018-10-26-6-4 CTM 670-December 2013 (Verified)
DIME Test ID: 2018-10-26-6-5 CTM 670-December 2013 (Verified)
DIME Test ID: 2018-10-26-6-6 CTM 670-December 2013 (Verified)
DIME Test ID: 2018-10-26-6-7 CTM 670-December 2013 (Verified)