Sample Record

Owner Lab

  • CT HQ - Sacramento Structural Materials Testing Laboratory

DIME Sample ID 2017-10-20-10

Sample is locked from editing. info

Project Information

Project IdentifiersProject ID: 211235
DEA: 054482U4
EFIS: 0500000543
DIST-CO-RTE-PM05-SB-101-2.2/3.3
Award Date06/20/2016
Closeout Date08/23/2021
Work DescriptionBUILD AND RECONSTRUCT BRIDGES, CONSTRUCT RAMPS AND FRONTAGE ROAD.
Location DescriptionSANTA BARBARA COUNTY IN CARPINTERIA FROM 0.2 MILE SOUTH OF CARPINTERIA CREEK BRIDGE TO FRANKLIN CREEK BRIDGE
QA Service Level1 (Verified on 07/27/2016)

Sample Information

Sample Taken Date10/20/2017 Sample Unique Key10
Will the laboratory/organization for which you are a member perform testing on this material sample?Yes Date that the sample was received by the laboratory/organization performing the testing10/24/2017
Sample typeQuality Assurance A brief description of the sample5, 6 mechanical couplers
The quantity of what the sample constitutes8 From where was the sample collectedJob Site
First name of sampler or witnessed byBeinavdo Last name of sampler or witnessed byHernandez
Title of samplerUnknown Telephone number of samplerUnknown
Laboratory sample identificationUnknown Linked DIME Sample IDUnknown
The fabricator/manufacturer/facility nameHarris Rebar Transportation Laboratory (TL) NumberC760207
Inspector Lot Number from the Transportation Laboratory (TL) Form05-4482U4 Structure unique identifierNot set
Structure nameNot set

Material Information

Material TypeSMTL TM5 - Couplers Production or Authorization TestingAuthorization Testing
Service or UltimateService Material Standard CodeASTM A706
Material Grade60 Rebar ManufacturerNucor
Coupler ManufacturerBarSplice Intermediate Assembler or FabricatorUnknown
Rebar Size5, 6 Coupler ModelBartec
Coating StandardsUncoated Shape of RebarStraight
Rebar Hoop DiameterUnknown Rebar Hoop FabricatorUnknown
Coupler Component Heat/Lot Number(s)11203080, DL14103837 Rebar Heat Number(s)SE17100706, SE17101027
Rebar Size 2 Not set Coupler Unique IDNot set

Submitted Tests

DIME Test IDTest MethodTester Name, Testing LabDate TestedSubmitted ByVerified?Release DateTest CommentsActions
2017-10-20-10-1CTM 670-December 2013: Method of Tests for Mechanical and Welded Reinforcing Steel Splices (Tensile Slip)Fred, CT HQ - Sacramento Structural Materials Testing Laboratory10/26/2017Fred
Yes
11/03/2017Service Splice
2017-10-20-10-2CTM 670-December 2013: Method of Tests for Mechanical and Welded Reinforcing Steel Splices (Tensile Slip)Fred, CT HQ - Sacramento Structural Materials Testing Laboratory10/26/2017Fred
Yes
11/03/2017Service Splice
2017-10-20-10-3CTM 670-December 2013: Method of Tests for Mechanical and Welded Reinforcing Steel Splices (Tensile Slip)Fred, CT HQ - Sacramento Structural Materials Testing Laboratory10/26/2017Fred
Yes
11/03/2017Service Splice
2017-10-20-10-4CTM 670-December 2013: Method of Tests for Mechanical and Welded Reinforcing Steel Splices (Tensile Slip)Fred, CT HQ - Sacramento Structural Materials Testing Laboratory10/26/2017Fred
Yes
11/03/2017Service Splice
2017-10-20-10-5CTM 670-December 2013: Method of Tests for Mechanical and Welded Reinforcing Steel Splices (Tensile Slip)Fred, CT HQ - Sacramento Structural Materials Testing Laboratory10/26/2017Fred
Yes
11/03/2017Service Splice
2017-10-20-10-6CTM 670-December 2013: Method of Tests for Mechanical and Welded Reinforcing Steel Splices (Tensile Slip)Fred, CT HQ - Sacramento Structural Materials Testing Laboratory10/26/2017Fred
Yes
11/03/2017Service Splice

Sample File Attachments

File NameExtensionDate UploadedActions
No results found.

Test File Attachments


DIME Test ID: 2017-10-20-10-1 CTM 670-December 2013 (Verified)
DIME Test ID: 2017-10-20-10-2 CTM 670-December 2013 (Verified)
DIME Test ID: 2017-10-20-10-3 CTM 670-December 2013 (Verified)
DIME Test ID: 2017-10-20-10-4 CTM 670-December 2013 (Verified)
DIME Test ID: 2017-10-20-10-5 CTM 670-December 2013 (Verified)
DIME Test ID: 2017-10-20-10-6 CTM 670-December 2013 (Verified)