Print Report | Back to Sample Detail

Sample Record for 2023-03-17-35

Note: Fields with no data or with a value of "Unknown" will not be displayed on the print out.

Project Information

Project ID: 215188 DEA: 080F5434 EFIS: 0817000239 Permit Numbers: 0823NMC0369 QA Service Level: 1
DIST-CO-RTE-PM: 08-RIV-I-15,SR-91-6.1-7.6
Work Description: I-15 ELC: 15/91 Express Lanes Connector Project (ELC)
Location Description: Junction of I-15 and SR-91 in Corona, CA
Contractor Name: Myers-Rados Joint Venture
Contractor Address: 629 N. Main Street, Suite C3, Corona, CA 92878
Resident Engineer: Roy Fisher Structure Rep.: Alhakem Alina

Sample Information

DIME Sample ID: 2023-03-17-35
TL Number from the TL Form:
Sample Submitted By Organization: CT D08 - Fontana Field Testing Laboratory
Sample Organization Contact: 9512323690
Type of Sample: Department Acceptance
Type of Material: Concrete
Sample Taken Date: 03/17/2023
Date that the sample was received by the laboratory/organization performing the testing: 03/18/2023
The quantity of what the sample constitutes: 4 Beams
A brief description of the sample: Concrete beams
From where was the sample collected: Job Site
Laboratory sample identification: 6J02A1,6J02A2,6J02B1,6J02B2
Structure unique identifier:
Structure name:
The fabricator/manufacturer/facility name: Cemex, Fontana

Material Information

The concrete mix design number: 1625994
The truck number from where the sample was collected:
The batch plant ticket number from where the sample was collected: 8
Concrete batch plant:
The fabricator/manufacturer designation for the sample:
A detailed description of where the material sample was collected: back of concrete truck
Where the material sample would have been placed if not sampled:
From Lot No.:
Bag Lot No.:

Test Results

Test 1 of 5

DIME Test ID: 2023-03-17-35-1
Test Method: CTM 533-June 2010: Method of Test for Ball Penetration in Fresh Portland Cement Concrete
Verified Date: 03/27/2023
Date Tested: 03/17/2023
Submitted By Organization: CT D08 - Fontana Field Testing Laboratory
Organization Address: 13970 Victoria Street,
Organization City: Fontana
Organization State: CA
Organization Zipcode: 92336
Organization Email: prakash.gowda@dot.ca.gov
Organization Phone: (951) 232-3690
General Comments for this Test:
Test Result Compliance:
Additional Comments When Verified:
Ball penetration in freshly mixed concrete (average) 2.75 inch

Test 2 of 5

DIME Test ID: 2023-03-17-35-2
Test Method: CTM 504-June 2010: Method of Test for Determining Air Content of Freshly Mixed Concrete by the Pressure Method
Verified Date: 03/27/2023
Date Tested: 03/17/2023
Submitted By Organization: CT D08 - Fontana Field Testing Laboratory
Organization Address: 13970 Victoria Street,
Organization City: Fontana
Organization State: CA
Organization Zipcode: 92336
Organization Email: prakash.gowda@dot.ca.gov
Organization Phone: (951) 232-3690
General Comments for this Test:
Test Result Compliance:
Additional Comments When Verified:
Air Content 1.4 %

Test 3 of 5

DIME Test ID: 2023-03-17-35-3
Test Method: CTM 518-June 2010: Method of Test for Unit Weight of Fresh Concrete
Verified Date: 03/27/2023
Date Tested: 03/17/2023
Submitted By Organization: CT D08 - Fontana Field Testing Laboratory
Organization Address: 13970 Victoria Street,
Organization City: Fontana
Organization State: CA
Organization Zipcode: 92336
Organization Email: prakash.gowda@dot.ca.gov
Organization Phone: (951) 232-3690
General Comments for this Test:
Test Result Compliance:
Additional Comments When Verified:
Unit weight of the concrete 149.8 lb/ft^3
Cement content 685.5 lb/yd^3

Test 4 of 5

DIME Test ID: 2023-03-17-35-4
Test Method: CTM 523-July 2012: Method of Test for Flexural Strength of Concrete
Verified Date: 03/27/2023
Date Tested: 03/24/2023
Submitted By Organization: CT D08 - Fontana Field Testing Laboratory
Organization Address: 13970 Victoria Street,
Organization City: Fontana
Organization State: CA
Organization Zipcode: 92336
Organization Email: prakash.gowda@dot.ca.gov
Organization Phone: (951) 232-3690
General Comments for this Test:
Test Result Compliance:
Additional Comments When Verified:
What test method is being used? Third-Point Loading
Fracture initiates in the tension surface Within the Middle Third of the Span Length
Modulus of rupture 580 psi

Test 5 of 5

DIME Test ID: 2023-03-17-35-5
Test Method: CTM 523-July 2012: Method of Test for Flexural Strength of Concrete
Verified Date: 03/27/2023
Date Tested: 03/24/2023
Submitted By Organization: CT D08 - Fontana Field Testing Laboratory
Organization Address: 13970 Victoria Street,
Organization City: Fontana
Organization State: CA
Organization Zipcode: 92336
Organization Email: prakash.gowda@dot.ca.gov
Organization Phone: (951) 232-3690
General Comments for this Test:
Test Result Compliance:
Additional Comments When Verified:
What test method is being used? Third-Point Loading
Fracture initiates in the tension surface Within the Middle Third of the Span Length
Modulus of rupture 570 psi