Project Information

Project ID: 99999 DEA: 0322222 QA Service Level:
DIST-CO-RTE-PM: 03-SAC,OMG-888,99,80-0.6-0.6
Work Description: THIS PROJECT RECORD WAS ADDED FOR DIME TESTERS - DATA SUBMITTED FOR THIS PROJECT SHOULD NOT BE USED FOR ANY OTHER PURPOSES.
Location Description: THIS PROJECT RECORD WAS ADDED FOR DIME TESTERS - DATA SUBMITTED FOR THIS PROJECT SHOULD NOT BE USED FOR ANY OTHER PURPOSES.
Contractor Name: Unknown
Contractor Address: Unknown
Resident Engineer: Michael Maksimovich Structure Rep.: Unknown

Sample Information

DIME Sample ID: 2020-03-16-1
TL Number from the TL Form:
Sample Submitted By Organization: CT HQ - Sacramento Hot Mix Asphalt Laboratory
Sample Organization Contact: (916) 227-7302
Type of Sample: Quality Control
Type of Material: Aggregate
Sample Taken Date: 03/16/2020
Date that the sample was received by the laboratory/organization performing the testing: 03/16/2020
The quantity of what the sample constitutes: JMF Submittal
A brief description of the sample: 1/2" Aggregate
From where was the sample collected: Source
Laboratory sample identification:
Structure unique identifier:
Structure name:
The fabricator/manufacturer/facility name: Vulcan Materials

Material Information

Source Identification (SMARA, name of Pit or Job Site): 91-01-0010::CALMAT/PLEASANTON
The fabricator's/manufacturer's product name for the sample:
The fabricator/manufacturer designation for the sample:
The plant number:
A detailed description of where the material sample was collected: 0.5 inch Bin
Where the material sample would have been placed if not sampled:
Primary Aggregate Nominal Size: 1/2 inch
The concrete mix design number:
Lot number:
Sublot number:
Aggregate Mix Number:

Test Results

Test 1 of 2

DIME Test ID: 2020-03-16-1-1
Test Method: AASHTO T27-14: Standard Method of Test for Sieve Analysis of Fine and Coarse Aggregates (Sieve Analysis)
Verified Date: 03/16/2020
Date Tested: 03/16/2020
Submitted By Organization: CT HQ - Sacramento Hot Mix Asphalt Laboratory
Organization Address: 5900 Folsom Boulevard, Room 225,
Organization City: Sacramento
Organization State: CA
Organization Zipcode: 95819
Organization Email: guadalupe.magana@dot.ca.gov
Organization Phone: (916) 227-7302
General Comments for this Test:
Test Result Compliance:
Additional Comments When Verified:
What type of gradation is being tested? HMA Gradation
Cumulative percent passing the 1 1/2 in. sieve 100 %
Cumulative percent passing the 1 in. sieve 100 %
Cumulative percent passing the 3/4 in. sieve 100 %
Cumulative percent passing the 1/2 in. sieve 73 %
Cumulative percent passing the 3/8 in. sieve 20 %
Cumulative percent passing the #4 sieve 4 %
Cumulative percent passing the #8 sieve 3 %
Cumulative percent passing the #16 sieve 2 %
Cumulative percent passing the #30 sieve 1 %
Cumulative percent passing the #50 sieve 1 %
Cumulative percent passing the #100 sieve 1 %
Cumulative percent passing the #200 sieve 1 %

Test 2 of 2

DIME Test ID: 2020-03-16-1-2
Test Method: AASHTO T27-14: Standard Method of Test for Sieve Analysis of Fine and Coarse Aggregates (Sieve Analysis)
Verified Date: 03/16/2020
Date Tested: 03/16/2020
Submitted By Organization: CT HQ - Sacramento Hot Mix Asphalt Laboratory
Organization Address: 5900 Folsom Boulevard, Room 225,
Organization City: Sacramento
Organization State: CA
Organization Zipcode: 95819
Organization Email: guadalupe.magana@dot.ca.gov
Organization Phone: (916) 227-7302
General Comments for this Test:
Test Result Compliance:
Additional Comments When Verified:
What type of gradation is being tested? HMA Gradation
Cumulative percent passing the 1 1/2 in. sieve 100 %
Cumulative percent passing the 1 in. sieve 100 %
Cumulative percent passing the 3/4 in. sieve 100 %
Cumulative percent passing the 1/2 in. sieve 100 %
Cumulative percent passing the 3/8 in. sieve 89 %
Cumulative percent passing the 1/4 in. sieve 89 %
Cumulative percent passing the #4 sieve 29 %
Cumulative percent passing the #8 sieve 5 %
Cumulative percent passing the #16 sieve 2 %
Cumulative percent passing the #30 sieve 1 %
Cumulative percent passing the #50 sieve 1 %
Cumulative percent passing the #100 sieve 1 %
Cumulative percent passing the #200 sieve 1 %