Gavin Newsom, Governor |
DEPARTMENT OF TRANSPORTATIONDIVISION OF ENGINEERING SERVICES MATERIALS ENGINEERING AND TESTING SERVICES Concrete Materials Testing Branch 5900 Folsom Blvd. Sacramento, CA 95819 916-227-7205 |
Contract # 030H26U4 Cty PLA Rte 65 PM R5.0/R6.6 Vendor # |
REPORT OF LABORATORY TESTING |
||||
Resident Engineer: |
Jeff Johnson |
Date Reported: |
06/25/2019 |
|
Address: |
TL Number: |
173147 |
||
City: |
||||
Project Name: NORTHBOUND WIDENING AND RAMP IMPROVEMENTS. |
||||
Prime Contractor: FLATIRON WEST INC |
||||
Sample Taken Date: |
05/28/2019 |
Mix Design: |
1605387 |
|
Contractor: Unknown |
Location : PLACER COUNTY IN AND NEAR ROSEVILLE AND ROCKLIN FROM 0.1 MILE SOUTH OF EAST ROSEVILLE VIADUCT TO 0.5 MILE SOUTH OF PLEASANT GROVE BOULEVARD OVERCROSSING |
|||
Structure unique identifier: |
||||
Structure name: |
||||
Location of Pour: Unknown |
The following testing has been tested in accordance with:
ASTM C39-17a : Standard Test Method for Compressive Strength of Cylindrical Concrete Specimens
Capped in accordance with ASTM C617/CTM521
Cured in accordance with ASTM C511
Specimen | Average diameter of cylinder (in) | Cross sectional area of cylinder (in^2) | Maximum load on cylinder (lb) | Compressive strength of cylinder (psi) | Type of fracture pattern of cylinder |
---|---|---|---|---|---|
1 | 6.02 | 28.45 | 179672 | 6315.4 | 1 |
2 | 6.01 | 28.35 | 183601 | 6476.2 | 1 |
DIME Test ID: 2019-05-28-2-1
Number of specimens: 2
Compressive strength (to nearest 10 psi): 6400
Age of specimen: 28 days
Certified By: Larry McCrum
*Subject to final inspection by the Resident Engineer. |
TL- Report of Laboratory Testing