Project ID: 99999 DEA: 0322222
QA Service Level:
DIST-CO-RTE-PM: 03-SAC,OMG-888,99,80-0.6-0.6
Work Description: THIS PROJECT RECORD WAS ADDED FOR DIME TESTERS - DATA SUBMITTED FOR THIS PROJECT SHOULD NOT BE USED FOR ANY OTHER PURPOSES.
Location Description: THIS PROJECT RECORD WAS ADDED FOR DIME TESTERS - DATA SUBMITTED FOR THIS PROJECT SHOULD NOT BE USED FOR ANY OTHER PURPOSES.
Contractor Name: Unknown
Contractor Address: Unknown
Resident Engineer: Michael Maksimovich Structure Rep.: Unknown
DIME Sample ID: 2017-11-01-22
TL Number from the TL Form:
Sample Submitted By Organization: CT HQ - Sacramento Materials Management Branch Field Office
Sample Organization Contact: (562) 500-5861
Type of Sample: Quality Control
Type of Material: Reclaimed Asphalt Pavement
Sample Taken Date: 11/01/2017
Date that the sample was received by the laboratory/organization performing the testing:
The quantity of what the sample constitutes: 1
A brief description of the sample: RAP ignition 2
From where was the sample collected: Source
Laboratory sample identification:
Structure unique identifier:
Structure name:
The fabricator/manufacturer/facility name: Test
DIME Test ID: 2017-11-01-22-1
Test Method: AASHTO T30-15: Standard Method of Test for Mechanical Analysis of Extracted Aggregate (Mechanical Analysis)
Verified Date: 11/03/2017
Date Tested: 11/03/2017
Submitted By Organization: CT HQ - Sacramento Materials Management Branch Field Office
Organization Address: 5900 Folsom Boulevard, MS 5,
Organization City: Sacramento
Organization State: CA
Organization Zipcode: 95819
Organization Email: brett.soldano@dot.ca.gov
Organization Phone: (562) 500-5861
General Comments for this Test:
Test Result Compliance:
Additional Comments When Verified:
Cumulative percent passing the 2 in. sieve
|
no data
|
Cumulative percent passing the 1 1/2 in. sieve
|
100 %
|
Cumulative percent passing the 1 in. sieve
|
100 %
|
Cumulative percent passing the 3/4 in. sieve
|
100 %
|
Cumulative percent passing the 1/2 in. sieve
|
100 %
|
Cumulative percent passing the 3/8 in. sieve
|
94.7 %
|
Cumulative percent passing the 1/4 in. sieve
|
68.1 %
|
Cumulative percent passing the #4 sieve
|
49.2 %
|
Cumulative percent passing the #8 sieve
|
45.6 %
|
Cumulative percent passing the #16 sieve
|
37.3 %
|
Cumulative percent passing the #30 sieve
|
29 %
|
Cumulative percent passing the #50 sieve
|
21.5 %
|
Cumulative percent passing the #100 sieve
|
15.3 %
|
Cumulative percent passing the #200 sieve
|
10.8 %
|
DIME Test ID: 2017-11-01-22-2
Test Method: AASHTO T308-10: Standard Method of Test for Determining the Asphalt Binder Content of Hot Mix Asphalt (HMA) by the Ignition Method (Method A) (Asphalt Binder Content)
Verified Date: 11/03/2017
Date Tested: 11/03/2017
Submitted By Organization: CT HQ - Sacramento Materials Management Branch Field Office
Organization Address: 5900 Folsom Boulevard, MS 5,
Organization City: Sacramento
Organization State: CA
Organization Zipcode: 95819
Organization Email: brett.soldano@dot.ca.gov
Organization Phone: (562) 500-5861
General Comments for this Test:
Test Result Compliance:
Additional Comments When Verified:
What temperature unit is used?
|
Fahrenheit
|
Test procedure used?
|
Method A
|
Mass of HMA Sample prior to ignition
|
no data
|
Corrected Asphalt Binder Content
|
6.58 %
|
Mass Loss
|
no data
|
Correction Factor (Percent by mass of HMA Specimen)
|
no data
|
Moisture Content
|
no data
|
Temperature Compensation Factor
|
no data
|
Test Temperature
|
no data
|