Project ID: 214337 DEA: 080E33U4 EFIS: 0817000075
QA Service Level: 1
DIST-CO-RTE-PM: 08-SBD-115-R7.3/R10.0
Work Description: ADD WB AUX & EB DECEL LANES, WIDEN I15 SW CONNECT,RAMPS/BRDG
Location Description: SAN BERNARDINO COUNTY IN ONTARIO FROM 0.2 MILE WEST OF CUCAMONGA CREEK BRIDGE TO MILLIKEN AVENUE
Contractor Name: Ames Construction
Contractor Address: 391 North Main Street, Suite 302, Corona, CA 92880
Resident Engineer: Denise Sostrom Structure Rep.: Matt Bruce
DIME Sample ID: 2023-10-22-3
TL Number from the TL Form:
Sample Submitted By Organization: CT D08 - Fontana Field Testing Laboratory
Sample Organization Contact: 9512323690
Type of Sample: Department Acceptance
Type of Material: Concrete
Sample Taken Date: 10/22/2023
Date that the sample was received by the laboratory/organization performing the testing: 10/25/2023
The quantity of what the sample constitutes: 12 Beams
A brief description of the sample: Rapid Set Concrete beams
From where was the sample collected: Job Site
Laboratory sample identification: R8-A1, R8-A2, R8-A3, R8-B1, R8-B2, R8-B3, R8-C1, R8-C2, R8-C3, R8-D1, R8-D2, R8-D3
Structure unique identifier:
Structure name:
The fabricator/manufacturer/facility name: Robertson's Ready Mix - Fontana
The concrete mix design number: SM446B2R
The truck number from where the sample was collected:
The batch plant ticket number from where the sample was collected: 8081699
Concrete batch plant:
The fabricator/manufacturer designation for the sample:
A detailed description of where the material sample was collected: back of concrete truck
Where the material sample would have been placed if not sampled:
From Lot No.:
Bag Lot No.:
DIME Test ID: 2023-10-22-3-1
Test Method: CTM 533-June 2010: Method of Test for Ball Penetration in Fresh Portland Cement Concrete
Verified Date: 11/20/2023
Date Tested: 10/22/2023
Submitted By Organization: CT D08 - Fontana Field Testing Laboratory
Organization Address: 13970 Victoria Street,
Organization City: Fontana
Organization State: CA
Organization Zipcode: 92336
Organization Email: prakash.gowda@dot.ca.gov
Organization Phone: (951) 232-3690
General Comments for this Test: Set A
Test Result Compliance:
Additional Comments When Verified:
|
Ball penetration in freshly mixed concrete (average)
|
2.5 inch
|
DIME Test ID: 2023-10-22-3-2
Test Method: CTM 504-June 2010: Method of Test for Determining Air Content of Freshly Mixed Concrete by the Pressure Method
Verified Date: 11/20/2023
Date Tested: 10/22/2023
Submitted By Organization: CT D08 - Fontana Field Testing Laboratory
Organization Address: 13970 Victoria Street,
Organization City: Fontana
Organization State: CA
Organization Zipcode: 92336
Organization Email: prakash.gowda@dot.ca.gov
Organization Phone: (951) 232-3690
General Comments for this Test: Set A
Test Result Compliance:
Additional Comments When Verified:
DIME Test ID: 2023-10-22-3-3
Test Method: CTM 518-June 2010: Method of Test for Unit Weight of Fresh Concrete
Verified Date: 11/20/2023
Date Tested: 10/22/2023
Submitted By Organization: CT D08 - Fontana Field Testing Laboratory
Organization Address: 13970 Victoria Street,
Organization City: Fontana
Organization State: CA
Organization Zipcode: 92336
Organization Email: prakash.gowda@dot.ca.gov
Organization Phone: (951) 232-3690
General Comments for this Test: CC not included. Set A
Test Result Compliance:
Additional Comments When Verified:
|
Unit weight of the concrete
|
148.8 lb/ft^3
|
|
Cement content
|
no data0 lb/yd^3
|
DIME Test ID: 2023-10-22-3-4
Test Method: CTM 524-March 2013: Method of Test for Flexural Strength Of Rapid Strength Concrete
Verified Date: 11/20/2023
Date Tested: 11/02/2023
Submitted By Organization: CT D08 - Fontana Field Testing Laboratory
Organization Address: 13970 Victoria Street,
Organization City: Fontana
Organization State: CA
Organization Zipcode: 92336
Organization Email: prakash.gowda@dot.ca.gov
Organization Phone: (951) 232-3690
General Comments for this Test: Set A
Test Result Compliance: complies
Additional Comments When Verified:
|
Number of specimens
|
3
|
|
Does the testing machine measure load or stress on the beam specimen?
|
Load
|
|
Fracture initiates in the tension surface
|
Within the Middle Third of the Span Length
|
|
Fracture occurred at a capped section
|
No
|
|
Is a beam dimensional correction factor used?
|
No
|
|
Age of specimen
|
10 days
|
|
Modulus of rupture
|
810 psi
|
|
Modulus of rupture 2
|
830 psi
|
|
Modulus of rupture average
|
820 psi
|
|
Modulus of rupture 3
|
810 psi
|
DIME Test ID: 2023-10-22-3-5
Test Method: CTM 533-June 2010: Method of Test for Ball Penetration in Fresh Portland Cement Concrete
Verified Date: 11/20/2023
Date Tested: 10/22/2023
Submitted By Organization: CT D08 - Fontana Field Testing Laboratory
Organization Address: 13970 Victoria Street,
Organization City: Fontana
Organization State: CA
Organization Zipcode: 92336
Organization Email: prakash.gowda@dot.ca.gov
Organization Phone: (951) 232-3690
General Comments for this Test: Set B
Test Result Compliance:
Additional Comments When Verified:
|
Ball penetration in freshly mixed concrete (average)
|
3.25 inch
|
DIME Test ID: 2023-10-22-3-6
Test Method: CTM 504-June 2010: Method of Test for Determining Air Content of Freshly Mixed Concrete by the Pressure Method
Verified Date: 11/20/2023
Date Tested: 10/22/2023
Submitted By Organization: CT D08 - Fontana Field Testing Laboratory
Organization Address: 13970 Victoria Street,
Organization City: Fontana
Organization State: CA
Organization Zipcode: 92336
Organization Email: prakash.gowda@dot.ca.gov
Organization Phone: (951) 232-3690
General Comments for this Test: Set B
Test Result Compliance:
Additional Comments When Verified:
DIME Test ID: 2023-10-22-3-7
Test Method: CTM 518-June 2010: Method of Test for Unit Weight of Fresh Concrete
Verified Date: 11/20/2023
Date Tested: 10/22/2023
Submitted By Organization: CT D08 - Fontana Field Testing Laboratory
Organization Address: 13970 Victoria Street,
Organization City: Fontana
Organization State: CA
Organization Zipcode: 92336
Organization Email: prakash.gowda@dot.ca.gov
Organization Phone: (951) 232-3690
General Comments for this Test: CC not included. Set B
Test Result Compliance:
Additional Comments When Verified:
|
Unit weight of the concrete
|
150.3 lb/ft^3
|
|
Cement content
|
no data0 lb/yd^3
|
DIME Test ID: 2023-10-22-3-8
Test Method: CTM 524-March 2013: Method of Test for Flexural Strength Of Rapid Strength Concrete
Verified Date: 11/20/2023
Date Tested: 11/02/2023
Submitted By Organization: CT D08 - Fontana Field Testing Laboratory
Organization Address: 13970 Victoria Street,
Organization City: Fontana
Organization State: CA
Organization Zipcode: 92336
Organization Email: prakash.gowda@dot.ca.gov
Organization Phone: (951) 232-3690
General Comments for this Test: Set B
Test Result Compliance: complies
Additional Comments When Verified:
|
Number of specimens
|
3
|
|
Does the testing machine measure load or stress on the beam specimen?
|
Load
|
|
Fracture initiates in the tension surface
|
Within the Middle Third of the Span Length
|
|
Fracture occurred at a capped section
|
No
|
|
Is a beam dimensional correction factor used?
|
No
|
|
Age of specimen
|
10 days
|
|
Modulus of rupture
|
820 psi
|
|
Modulus of rupture 2
|
810 psi
|
|
Modulus of rupture average
|
810 psi
|
|
Modulus of rupture 3
|
790 psi
|
DIME Test ID: 2023-10-22-3-9
Test Method: CTM 533-June 2010: Method of Test for Ball Penetration in Fresh Portland Cement Concrete
Verified Date: 11/20/2023
Date Tested: 10/23/2023
Submitted By Organization: CT D08 - Fontana Field Testing Laboratory
Organization Address: 13970 Victoria Street,
Organization City: Fontana
Organization State: CA
Organization Zipcode: 92336
Organization Email: prakash.gowda@dot.ca.gov
Organization Phone: (951) 232-3690
General Comments for this Test: Set C
Test Result Compliance:
Additional Comments When Verified:
|
Ball penetration in freshly mixed concrete (average)
|
3.25 inch
|
DIME Test ID: 2023-10-22-3-10
Test Method: CTM 504-June 2010: Method of Test for Determining Air Content of Freshly Mixed Concrete by the Pressure Method
Verified Date: 11/20/2023
Date Tested: 10/23/2023
Submitted By Organization: CT D08 - Fontana Field Testing Laboratory
Organization Address: 13970 Victoria Street,
Organization City: Fontana
Organization State: CA
Organization Zipcode: 92336
Organization Email: prakash.gowda@dot.ca.gov
Organization Phone: (951) 232-3690
General Comments for this Test: Set C
Test Result Compliance:
Additional Comments When Verified:
DIME Test ID: 2023-10-22-3-11
Test Method: CTM 518-June 2010: Method of Test for Unit Weight of Fresh Concrete
Verified Date: 11/20/2023
Date Tested: 10/23/2023
Submitted By Organization: CT D08 - Fontana Field Testing Laboratory
Organization Address: 13970 Victoria Street,
Organization City: Fontana
Organization State: CA
Organization Zipcode: 92336
Organization Email: prakash.gowda@dot.ca.gov
Organization Phone: (951) 232-3690
General Comments for this Test: CC not included. Set c
Test Result Compliance:
Additional Comments When Verified:
|
Unit weight of the concrete
|
149.2 lb/ft^3
|
|
Cement content
|
no data0 lb/yd^3
|
DIME Test ID: 2023-10-22-3-12
Test Method: CTM 524-March 2013: Method of Test for Flexural Strength Of Rapid Strength Concrete
Verified Date: 11/20/2023
Date Tested: 11/02/2023
Submitted By Organization: CT D08 - Fontana Field Testing Laboratory
Organization Address: 13970 Victoria Street,
Organization City: Fontana
Organization State: CA
Organization Zipcode: 92336
Organization Email: prakash.gowda@dot.ca.gov
Organization Phone: (951) 232-3690
General Comments for this Test: Set C
Test Result Compliance: complies
Additional Comments When Verified:
|
Number of specimens
|
3
|
|
Does the testing machine measure load or stress on the beam specimen?
|
Load
|
|
Fracture initiates in the tension surface
|
Within the Middle Third of the Span Length
|
|
Fracture occurred at a capped section
|
No
|
|
Is a beam dimensional correction factor used?
|
No
|
|
Age of specimen
|
10 days
|
|
Modulus of rupture
|
750 psi
|
|
Modulus of rupture 2
|
790 psi
|
|
Modulus of rupture average
|
760 psi
|
|
Modulus of rupture 3
|
750 psi
|
DIME Test ID: 2023-10-22-3-13
Test Method: CTM 533-June 2010: Method of Test for Ball Penetration in Fresh Portland Cement Concrete
Verified Date: 11/20/2023
Date Tested: 10/23/2023
Submitted By Organization: CT D08 - Fontana Field Testing Laboratory
Organization Address: 13970 Victoria Street,
Organization City: Fontana
Organization State: CA
Organization Zipcode: 92336
Organization Email: prakash.gowda@dot.ca.gov
Organization Phone: (951) 232-3690
General Comments for this Test: Set D
Test Result Compliance:
Additional Comments When Verified:
|
Ball penetration in freshly mixed concrete (average)
|
2.5 inch
|
DIME Test ID: 2023-10-22-3-14
Test Method: CTM 504-June 2010: Method of Test for Determining Air Content of Freshly Mixed Concrete by the Pressure Method
Verified Date: 11/20/2023
Date Tested: 10/23/2023
Submitted By Organization: CT D08 - Fontana Field Testing Laboratory
Organization Address: 13970 Victoria Street,
Organization City: Fontana
Organization State: CA
Organization Zipcode: 92336
Organization Email: prakash.gowda@dot.ca.gov
Organization Phone: (951) 232-3690
General Comments for this Test:
Test Result Compliance:
Additional Comments When Verified:
DIME Test ID: 2023-10-22-3-15
Test Method: CTM 518-June 2010: Method of Test for Unit Weight of Fresh Concrete
Verified Date: 11/20/2023
Date Tested: 10/23/2023
Submitted By Organization: CT D08 - Fontana Field Testing Laboratory
Organization Address: 13970 Victoria Street,
Organization City: Fontana
Organization State: CA
Organization Zipcode: 92336
Organization Email: prakash.gowda@dot.ca.gov
Organization Phone: (951) 232-3690
General Comments for this Test: CC not included. Set D.
Test Result Compliance:
Additional Comments When Verified:
|
Unit weight of the concrete
|
149.2 lb/ft^3
|
|
Cement content
|
no data0 lb/yd^3
|
DIME Test ID: 2023-10-22-3-16
Test Method: CTM 524-March 2013: Method of Test for Flexural Strength Of Rapid Strength Concrete
Verified Date: 11/20/2023
Date Tested: 11/02/2023
Submitted By Organization: CT D08 - Fontana Field Testing Laboratory
Organization Address: 13970 Victoria Street,
Organization City: Fontana
Organization State: CA
Organization Zipcode: 92336
Organization Email: prakash.gowda@dot.ca.gov
Organization Phone: (951) 232-3690
General Comments for this Test: Set D
Test Result Compliance: complies
Additional Comments When Verified:
|
Number of specimens
|
3
|
|
Does the testing machine measure load or stress on the beam specimen?
|
Load
|
|
Fracture initiates in the tension surface
|
Within the Middle Third of the Span Length
|
|
Fracture occurred at a capped section
|
No
|
|
Is a beam dimensional correction factor used?
|
No
|
|
Age of specimen
|
10 days
|
|
Modulus of rupture
|
710 psi
|
|
Modulus of rupture 2
|
710 psi
|
|
Modulus of rupture average
|
710 psi
|
|
Modulus of rupture 3
|
720 psi
|