2023-09-03-45-1 | CTM 524-March 2013: Method of Test for Flexural Strength Of Rapid Strength Concrete | 10/13/2023 | Not scheduled | IGNACIO ARECHIGA | CT D04 - Richmond Field Laboratory | Beam Set 22 A
Beams PASSED
Vanguard Mobile Hercules Plant A | |
2023-09-03-45-2 | CTM 524-March 2013: Method of Test for Flexural Strength Of Rapid Strength Concrete | 10/13/2023 | Not scheduled | IGNACIO ARECHIGA | CT D04 - Richmond Field Laboratory | Beams PASSED
Beam Set 23 C
Vanguard Mobile Hercules Plant C | |
2023-09-03-45-3 | CTM 524-March 2013: Method of Test for Flexural Strength Of Rapid Strength Concrete | 10/13/2023 | Not scheduled | IGNACIO ARECHIGA | CT D04 - Richmond Field Laboratory | Beams PASSED
Beam Set 28 A
Vanguard Mobile Hercules Plant A | |
2023-09-03-45-4 | CTM 524-March 2013: Method of Test for Flexural Strength Of Rapid Strength Concrete | 10/13/2023 | Not scheduled | IGNACIO ARECHIGA | CT D04 - Richmond Field Laboratory | Beams Passed
Vanguard Mobile Hercules Plant
Beam Set 27 B | |
2023-09-03-45-5 | CTM 524-March 2013: Method of Test for Flexural Strength Of Rapid Strength Concrete | 10/13/2023 | Not scheduled | IGNACIO ARECHIGA | CT D04 - Richmond Field Laboratory | Beams PASSED
Beam Set 26 C
Vanguard Mobile Hercules Plant C | |
2023-09-03-45-6 | CTM 524-March 2013: Method of Test for Flexural Strength Of Rapid Strength Concrete | 10/13/2023 | Not scheduled | IGNACIO ARECHIGA | CT D04 - Richmond Field Laboratory | Beams PASSED
Vanguard Mobile Hercules Plant D
Beam Set 25 D | |
2023-09-03-45-7 | CTM 524-March 2013: Method of Test for Flexural Strength Of Rapid Strength Concrete | 10/13/2023 | Not scheduled | IGNACIO ARECHIGA | CT D04 - Richmond Field Laboratory | Beams PASSED
Beam Set 24 A
Vanguard Mobile Hercules Plant A | |
2023-09-03-45-8 | CTM 524-March 2013: Method of Test for Flexural Strength Of Rapid Strength Concrete | 10/13/2023 | Not scheduled | IGNACIO ARECHIGA | CT D04 - Richmond Field Laboratory | Beams PASSED
Beam Set 32 D
Vanguard Mobile Hercules Plant D | |
2023-09-03-45-9 | CTM 524-March 2013: Method of Test for Flexural Strength Of Rapid Strength Concrete | 10/13/2023 | Not scheduled | IGNACIO ARECHIGA | CT D04 - Richmond Field Laboratory | Beams PASSED
Beam Set 31 C
Vanguard Mobile Hercules Plant C | |
2023-09-03-45-10 | CTM 524-March 2013: Method of Test for Flexural Strength Of Rapid Strength Concrete | 10/13/2023 | Not scheduled | IGNACIO ARECHIGA | CT D04 - Richmond Field Laboratory | Beams PASSED
Beam Set 35 B
Vanguard Mobile Hercules Plant B | |
2023-09-03-45-11 | CTM 524-March 2013: Method of Test for Flexural Strength Of Rapid Strength Concrete | 10/13/2023 | Not scheduled | IGNACIO ARECHIGA | CT D04 - Richmond Field Laboratory | 2-34C
Vanguard Mobile Hercules Plant
Beams PASSED | |